Ferry Road & Riverbend CSO Master Plan projects
We are changing the existing combined sewer system to:
- Reduce basement flooding
- Reduce combined sewer overflows
- Improve land drainage (rainwater and snowmelt)
- Support future sewer system upgrades
Construction of Contract 6 started in 2025. We are constructing a new land drainage trunk sewer that will flow into the Assiniboine River.
We estimate the cost of this new sewer will be approximately $36.5 million.
This work is part of the Combined Sewer Overflow (CSO) Master Plan.
Residents who live in the St. James ward can find out more about current traffic impacts here.
You can learn more about the work planned for each project in the “Contracts” section below.
| No. | Start date | Completion | Estimated cost | Scope of work |
|---|---|---|---|---|
| 6 | 2025 | 2026 | $36.5 million | Construction of a new land drainage trunk sewer approximately through the western part of Bourkevale Park, along Rutland Street from Portage Avenue to Silver Avenue, then through St. James Memorial Sports Park ending near the projection of St. Matthews Avenue. |