Completed Park projects
Armstrong Park Redevelopment
1030 Munroe Ave
Project:
New pathway, firepit, tree planting and site furniture plus upgrades to the existing shelter
Status:
Tender closed but not awarded
Completion Date:
Summer 2023
Ward: Elmwood - East Kildonan
Art McOuat Memorial Park
910 Maginot St
Project:
Baseball backstop renewal
Status:
Complete
Completion Date:
Fall 2023
Ward: St. Boniface
Barry Park
808 Barry Ave
Project:
Passive conversion
Status:
Complete
Completion Date:
Summer 2023
Ward: Transcona
Beauchemin Park
5921 Southboine Dr
Project:
Playground redevelopment
Status:
Complete
Completion Date:
Fall 2023
Ward: Charleswood - Tuxedo - Westwood
Broadway Neighbourhood Centre Park
185 Young St
Project:
Playground redevelopment
Status:
Complete
Completion Date:
Fall 2023
Ward: Fort Rouge - East Fort Garry
Clara Hughes Park and Playground Improvements
400 Matheson Ave
Project:
Decommissioning old wading pool. Upgrading existing playground and sports field plus drainage improvements.
Status:
Under construction
Completion Date:
Summer 2022
Ward: Mynarski
Corydon Community Centre - Crescentwood Site
1170 Corydon Ave
Project:
Playground renewal
Status:
Complete
Completion Date:
Fall 2023
Ward: River Heights - Fort Garry
Fountainview Park
70 Shorehill Blvd
Project:
Playground renewal
Status:
Complete
Completion Date:
Summer 2023
Ward: St. Vital
Inglewood Park Playground Redevelopment
295 Inglewood St
Project: Playground redevelopment
Status: Upgrading existing playground and site furniture
Completion Date: Summer 2023
Ward: St. James
Giizhigooweyaabikwe Park
242 Lizzie St
Project: Sport court redevelopment
Status: Complete
Completion Date: Summer 2023
Ward: Point Douglas
Hiddleston Park
38 Hiddleston Cres
Project: Playground redevelopment
Status: Complete
Completion Date: Fall 2023
Ward: Old Kildonan
Jill Officer Park Tennis Court Reconstruction
1410 Rothesay St
Project: Tennis court reconstruction
Status: Complete
Completion Date: November 2022
Ward: North Kildonan
Joe Malone Park
55 Boulton Bay
Project: Tennis court rehabilitation
Status: Complete
Completion Date: October 2022
Ward: River Heights - Fort Garry
Kern Park Playground Redevelopment
50 Kern Dr
Project: Playground renovation
Status: Construction anticipated Spring 2022
Completion Date: Summer 2023
Ward: Transcona
Kildonan Meadows South Park Playground Redevelopment
195 Kildonan Meadow Dr
Project: Upgrading existing pathways, playground and site furniture
Status: Tender closed but not awarded
Completion Date: Spring 2023
Ward: Transcona
Kirby/Setter Park Playground Redevelopment
575 Setter St
Project: Upgrading existing age 2-5 playground and site furniture
Status: Tender closed but not awarded
Completion Date: Spring 2023
Ward: St. James
Linwood Street Memorial Plaza
Yellow Ribbon Trail at Linwood St
Project: Memorial plaza
Status: Complete
Completion Date: Summer 2023
Ward: St. James
Maples Community Centre
40 Maberley Rd
Project: Cricket pitch upgrade
Status: Complete
Completion Date: Summer 2023
Ward: Old Kildonan
Marcy Beaucage Park/Roblin Park Community Centre
640 Pepperloaf Cres
Project: Playground expansion
Status: Complete
Completion Date: Summer 2023
Ward: Charleswood - Tuxedo - Westwood
McLeod Park
682 McLeod Ave
Project: Pathways
Status: Complete
Completion Date: Summer 2023
Ward: North Kildonan
Pinehurst Byron Park
41 Pinehurst Cres
Project: Pathway improvements
Status: Complete
Completion Date: Summer 2023
Ward: Charleswood - Tuxedo - Westwood
St. James Memorial Sports Park Pickleball Complex Construction
100 Sunset Blvd
Project: Pickleball court construction
Status: Complete
Completion Date: October 2022
Ward: St. James
St. Vital Memorial Park Basketball Court Construction
100 Sunset Blvd
Project: Basketball court construction
Status: Complete
Completion Date: Summer 2023
Ward: St. Vital
Sun Valley Park North Playground Redevelopment
125 Sun Valley Dr
Project: Upgrading existing playground and site furniture
Status: Awarded
Completion Date: Fall 2022
Ward: North Kildonan
Tokarz Park Playground Redevelopment
840 Beecher Ave
Project: Playground redevelopment
Status: Construction anticipated Summer 2022
Completion Date: Summer 2023
Ward: Old Kildonan
Valley Gardens Community Centre
901 Kimberly Ave
Project: Baseball backstop renewal
Status: Complete
Completion Date: Summer 2023
Ward: Elmwood - East Kildonan
William Johnstone Park
173 Vista Ave
Project: Outdoor classroom / new seating / pathway upgrades
Status: Complete
Completion Date: Summer 2023
Ward: St. Vital