Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
Public Works

2020-2021 Day/Pandora/Lagimodiere/Regent Pavement Renewals Project

This project is now complete

Ce projet est terminé

The 2020-2021 Day/Pandora/Lagimodiere/Regent Pavement Renewals Project is supported by the Government of Canada's New Building Canada Fund and the Province of Manitoba. It will see major reconstruction work that will greatly improve surface conditions for drivers, cyclists, and pedestrians and will increase safety for all users.


Updates

May 11, 2021 – Construction on Regent Avenue West from Rougeau Avenue to Plessis Road will begin on May 12, 2021. Please see the construction notice for staging information and traffic implications.

Background

The 2020-2021 Day/Pandora/Lagimodiere/Regent Pavement Renewals Project is supported by the Government of Canada's New Building Canada Fund and the Province of Manitoba. It will see major reconstruction work that will greatly improve surface conditions for drivers, cyclists, and pedestrians and will increase safety for all users.

The following streets are included in the project:

  • Day Street (Regent Avenue to Pandora Avenue)
  • Pandora Avenue E (Day Street to Wayoata Street)
  • Lagimodiere Boulevard
    • Northbound (Regent Avenue W to Almey Avenue)
    • Southbound (Reenders Drive to Regent Avenue W)
  • Regent Avenue W (Rougeau Avenue to Plessis Road)

The project takes place on critical regional streets that see a combined 100,000 vehicles daily, and sit adjacent to residences and businesses that will be directly affected by construction. The project team is working closely with various City departments to mitigate impacts to parking, Transit service, and both business and residential access through construction.

The City will reach out to and meet with businesses, residents, and property owners as required in each project area to gather information about parking and loading needs, accessibility, and access; this information will help us stage construction to reduce impact on area stakeholders and make accommodations where possible.

Up-to-date information about staging, access, and other construction-related topics will be posted on this webpage throughout the project.

If you own or lease property in these areas and believe you may be impacted by these projects, please feel free to reach out to Adam Prokopanko at aprokopanko@dillon.ca

Project Timeline

timeline

Timeline

Documents

Document Name Date Type
Regent construction notice 2021-05-11 Community Letters

Frequently Asked Questions

Open all | Close all

What is the 2020-2021 Day/Pandora/Lagimodiere/Regent Pavement Renewals Project?

This project is a renewal project, which means the roads will be rehabilitated and reconstructed to increase their lifespan and improve their condition. Work will include installing a new road surface, as well as cycling and sidewalk infrastructure. The designs include operational and geometric improvements, and upgrades to meet pedestrian accessibility standards.

What streets are included in the project?
  • Day Street (Regent Avenue to Pandora Avenue)
  • Pandora Avenue E (Day Street to Wayoata Street)
  • Lagimodiere Boulevard
    • Northbound (Regent Avenue W to Almey Avenue)
    • Southbound (Reenders Drive to Regent Avenue W)
  • Regent Avenue W (Rougeau Avenue to Plessis Road)
What type of work will be happening on these streets?
  • Day Street will be rehabilitated with extensive concrete repairs, curb replacement, sidewalk renewal at various locations, and a new asphalt surface.
  • Pandora Avenue E will be completely reconstructed with new concrete pavement, curbs, along with the construction of a new multi-use pathway and rehabilitation of the sidewalks as needed. Pandora Avenue E will also be lowered slightly to improve drainage in the boulevards.
  • Lagimodiere Boulevard will be a mill and fill rehabilitation with minor concrete repairs and a new asphalt surface.
  • Regent Avenue will be resurfaced with a new asphalt overlay on the existing concrete after the completion of minor concrete road repairs and sidewalk rehabilitation as required.
When will construction occur?
  • September 2020 – May 2021: Lagimodiere Boulevard
  • May – June 2021: Regent Avenue W
  • June – October 2021: Day Street and Pandora Avenue E
How will pedestrian safety be considered?

Pedestrian facilities will be designed according to the latest accessibility standards and will also focus on serving individuals with visual impairments. New design features include yellow detectable warning tiles, realigned pedestrian crossings, and improved sightlines to assist drivers in navigating through pedestrian crossings.

Will there be any improvements to cycling facilities?

A new multiuse pathway for cyclists and other active transportation users will be constructed along Pandora Avenue E in the existing wide north boulevard. This will be in addition to the existing sidewalk.

How will the City inform major stakeholders?

We will meet individually with major stakeholders through the planning and design phase of the project to provide information on location-specific impacts, and to determine specific needs during staging. Major stakeholders include large local businesses, schools, places of worship, and community centres on or adjacent to the project streets.

How will construction affect stakeholders?

We are attempting to mitigate major concerns, and will work with stakeholders to minimize construction impacts. Some impacts are inevitable and include:

  • Lane reductions
  • Street closures on Pandora Avenue E
  • Parking removal and restrictions
  • Reduced access from intersecting local streets and alleys
  • Bus stop relocations or temporary stop cancellations, and bus route detours

If you feel you may be affected by the construction phase (but have not yet heard from us), please reach out directly to Adam Prokopanko at aprokopanko@dillon.ca.

How will construction affect traffic and parking in the area?

As with any road construction project, there will be traffic implications. We are working on the development of traffic management and construction staging plans that minimize the impact to all road users while ensuring construction can be completed quickly and efficiently. We will be initiating proactive public communications once staging is complete to ensure the public is aware of staging, rerouting, lane closures, parking restrictions/removal, and project progress.

How will construction affect Transit services?

Transit services will be maintained throughout construction using various means such as stop relocations, temporary stop closures, and detours. All disruptions will be marked in advance of taking effect.

How can residents and businesses raise questions or concerns regarding the project?

We encourage those who feel they may be affected but have not yet heard from us to reach out directly to Adam Prokopanko at aprokopanko@dillon.ca.

We are doing our best to reach stakeholders in a timely and efficient manner but also understand that normal is changing every day and people may no longer be reachable where, or how, we once expected.

If you are a stakeholder on an upcoming project and have new or temporary contact information, please reach out to PWDCommunications@winnipeg.ca.

I own a property or run a business in the area of an upcoming construction project, but am currently staying home. How will I get the information I need and provide input on this project?

Please reach out to us. Send an email to PWDCommunications@winnipeg.ca and we will have the project team contact you.

Map

Map

Map

Last update: March 25, 2022

Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.