Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links

Labour Day – Monday, September 7. View holiday hours for City of Winnipeg facilities and services.

Labour Day – Monday, September 7. View holiday hours for City of Winnipeg facilities and services.

Public Works

Downtown Street Renewals 2026-2028

Over the next three years, the City of Winnipeg will repair and improve several downtown streets. A lot of these roads are old, damaged, or not suitable for how people get around today—whether they walk, bike, drive, or take the bus. The Downtown Street Renewals project will make these streets safer, smoother, and easier for everyone to use.


Background

Over the next three years, the City of Winnipeg will repair and improve several downtown streets. A lot of these roads are old, damaged, or not suitable for how people get around today—whether they walk, bike, drive, or take the bus. The Downtown Street Renewals project will make these streets safer, smoother, and easier for everyone to use.

This project is part of Winnipeg's plan to make roads and transportation better for everyone. The City is following important guides like the Transportation Master Plan and the Pedestrian and Cycling Strategies to help improve safety, make it easier for people to get around, protect the environment, and help the city grow. Fixing downtown streets isn't just about new pavement—it's about building streets that work for a modern city where everyone is included. Improvements will be made to roads, sidewalks, curbs, and street lights. Connections for people walking and biking will also be improved.

The project is in the planning and design stage. When the plans are ready, we will share more details about when construction will start and how it might affect people's living and working in the area. We will make sure to keep everyone updated at each stage of the project.

If you have questions or want to learn more about this project, please check back or subscribe below for updates, or contact the City of Winnipeg's project team. 

SubscribeInscription
Subscribe to project emails Inscription aux courriels sur le projet
Privacy StatementDéclaration de confidentialité Your personal information is being collected in accordance with s.36(1)(b) of The Freedom of Information and Protection of Privacy Act. This information will be used to manage your subscription and notification preferences. Your information will not be used or disclosed for any other purposes, except as authorized by law. If you have any questions about the collection of this information, contact the Corporate Access and Privacy Officer by mail to City Clerk’s Department, Administration Building, 510 Main Street, Winnipeg MB, R3B 1B9, or by telephone at 311. Vos renseignements personnels sont recueillis au titre de l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée. Ils seront utilisés pour gérer votre abonnement et vos préférences. Ils ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Si vous avez des questions sur la collecte de ces renseignements, veuillez communiquer avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville en écrivant au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou en composant le 311.

You can unsubscribe from this list anytime. Vous pouvez vous désinscrire quand vous voulez.

You can subscribe to this list again at any time. Vous pouvez vous réinscrire quand vous voulez.

Project Timeline

Project timeline

Documents

Document Name Date Type
Stakeholder meeting 2026-03-19 Storyboards
St. Mary water main notice 2026-04-16 Community letter
Edmonton St 1st construction notice 2026-04-13 Community letter
St. Mary Ave 1st construction notice 2026-04-13 Community letter
Kennedy St 1st construction notice 2026-04-14 Community letter

Frequently Asked Questions

Open all | Close all

What is the Downtown Street Renewals project?

The Downtown Street Renewals project is a plan by the City of Winnipeg to repair and improve several streets in the downtown area over the next three years. A lot of these roads are old, damaged, or not suitable for how people get around today—whether they walk, bike, drive, or take the bus. The project will make these streets safer, smoother, and easier for everyone to use.

Why is the City undertaking this project?

The City is undertaking this project because many downtown streets are old, damaged, or not suitable for how people get around today. By following important plans like the Transportation Master Plan and the Pedestrian and Cycling Strategies, the City wants to make streets safer and easier for everyone to use. This means making improvements to roads, sidewalks, curbs, and street lights so people walking or biking have better connections and everyone can get around more easily.

When will construction begin?

Locations included as part of the project are:

  • Hargrave St from Ellice Ave to Notre Dame Ave
  • Hargrave St from St. Mary Ave to Graham Ave
  • Carlton St. From Notre Dame Ave to Ellice Ave
  • Carlton St from Portage Ave to St. Mary Ave
  • Carlton St from York Ave to Broadway Ave
  • Edmonton St from Broadway Ave to Portage Ave
  • Kennedy St from Ellice Ave to Cumberland Ave
  • Kennedy St from Portage Ave to Broadway Ave
  • St. Mary Ave from Memorial Blvd to Edmonton St
  • York Ave from Memorial Blvd to Edmonton St
What changes are being considered?

The project will make many changes to the streets and sidewalks in the area. Here are some of the improvements being planned:

  • Fixing and upgrading roads, sidewalks, and curbs so they are safer and easier for everyone to use.
  • Putting in new street lights and repairing things underground, like pipes and cables.
  • Building protected bike lanes and raised bike paths for people who ride bikes.
  • Making intersections safer and easier for everyone to cross.
  • Improving sidewalks and spaces for people to walk and ride bikes.
  • Adding better benches, plants, lights, and places to park bikes.
  • New features to make the area more welcoming and easier to use for people of all abilities.

These changes will help make downtown safer, more comfortable, and easier for everyone to get around.

How will safety be addressed?

Making the streets safer is very important for this project. Experts will carefully check the roads for safety and use special designs at intersections to help everyone stay safe. The project will work on ways to prevent accidents and make sure people walking, biking, and driving can all get around easily.

How will walking and cycling be improved?

The project will make the downtown cycling network safer and easier to use by changing regular bike lanes into protected bike lanes and creating raised paths for bikes, where needed. Sidewalks will be fixed or kept the same as much as possible, and better signs will help people find their way when walking.

What about parking and loading?

Parking is important for downtown. The project will look at how wide the lanes are to make sure people can still have parking, wherever possible. The team will also make sure businesses can still get deliveries and people can get to stores during construction.

How will construction be staged?

Construction will be planned in steps so there is less disruption. There will be clear plans for how cars, trucks, buses, and bikes can get around during the construction. The team will make sure there is still parking and that people can get to businesses during construction.

Will any properties be affected?

Many properties along the project route will be affected while the work is happening. The project team will do their best to limit problems by planning the work in steps, keeping parking and access available as much as possible, and making sure stores and businesses are easy to get to.

How can I stay informed or get involved?

Please subscribe for project updates. You can also contact the project team via email at mark.vogt@wsp.com.

Last update: April 17, 2026

Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.