Sewage treatment plants
- Introduction
- North End Sewage Treatment Plant
- South End Sewage Treatment Plant
- West End Sewage Treatment Plant
Sewage treatment plants
Our sewer systems collect wastewater from industry, commercial businesses and homes. From there, it is sent to one of our three wastewater treatment plants:
What do NEWPCC, SEWPCC and WEWPCC mean?
In the past, our sewage treatment plants were called water pollution control centres. The North End Sewage Treatment Plant was formerly known as the North End Water Pollution Control Centre, or the acronym NEWPCC. SEWPCC refers to the South End Sewage Treatment Plant and WEWPCC refers to the West End Sewage Treatment Plant. When referring to the three treatment plants, many people still use the old acronyms.
How does wastewater treatment work?
We treat wastewater to remove the major contaminants (carbon, nitrogen and phosphorus) and harmful bacteria, such as E. coli. To do this, we send the raw sewage through several processes in our plants. Bacteria called activated sludge plays a major role in the treatment process. The activated sludge bacteria use the contaminants in the sewage as food to reproduce. Once this treatment cycle is completed, the activated sludge is removed, the treated water is disinfected, and it is sent to the river.
This process has been used worldwide since 1914 and has been used in Winnipeg since 1964, when we commissioned our first activated sludge plant at the NEWPCC to remove carbon. In 2008, the West End Sewage Treatment Plant (WEWPCC) activated sludge process was upgraded to remove not only carbon but also nitrogen and phosphorus. The South End Sewage Treatment Plant (SEWPCC) and North End Sewage Treatment Plant (NEWPCC) are now being upgraded to also remove all three contaminants.
Pre-treatment
Screens are used to remove plastics, rags, and other debris from the incoming raw wastewater. After screening, sand and grit settles to the bottom. The sand and grit are removed and trucked away to the Brady Road Resource Management Facility for disposal.
Primary treatment
Next the wastewater moves into sedimentation tanks, where approximately 65% of the suspended material settles to the bottom of the tank. In addition to material that settles in the bottom of the tanks, grease and oil that floats to the surface is removed by paddles or skimmers. Primary treatment takes several hours before the wastewater moves to the next stage of treatment.
Secondary treatment
After Primary Treatment, the wastewater flows into bioreactors which contain a mixture of micro-organisms that feed on the carbon in the wastewater. Oxygen is fed into the bioreactor so the micro-organisms can metabolize the carbon they're feeding on. This process also takes several hours. The activated sludge, or biomass, must be separated from the treated wastewater. The separation takes place in another group of sedimentation tanks called Secondary Clarifiers.
Final Clarification
In the final clarifier tanks, the biomass from the bioreactors settles out by gravity. About 25 to 50% of the settled biomass is returned to the head of each bioreactor to begin the process again.
The biomass that is reused provides a constant source of micro-organisms to the incoming wastewater for treatment. Because the biological growth within the bioreactors produces more biomass than is needed, some of it must be removed.
This excess biomass, called Waste Activated Sludge, is pumped to the Digesters, where it decomposes. All the material that settles in the Primary Clarifiers is also pumped to the Digesters.
Digestion, Dewatering and Solids Disposal
During digestion, the anaerobic bacteria break down the solids over the course of about 15 days. About half of the solids are destroyed during this process.
In the Digesters, a different type of bacteria, called anaerobes, feed on the carbon in the solids to produce biogases—mainly carbon dioxide and methane. Methane is recovered at the North End Sewage Treatment Plant (NEWPCC) and used to heat the Digesters and other buildings.
Once digestion is complete, excess water must be removed from the digested sludge. Dewatering is accomplished using high speed mechanical centrifuges. The liquid produced during dewatering is returned to another activated sludge process designed specifically to remove ammonia and nitrogen produced during digestion.
Digested material contains about 2% solids but is thickened to about 25% before being transported. The thickening process significantly reduces the volume of material that must be transported for final disposal.The thickened solids, now called biosolids, are trucked to the Brady Road Resource Management Facility. On average, Brady Road receives 36,000 kg of biosolids each day for final disposal.
North End Sewage Treatment Plant (NEWPCC)
Located at 2230 Main Street, the North End Sewage Treatment Plant (NEWPCC) processes approximately 60 percent of the wastewater treated in Winnipeg.
Plant Summary
- Population served: 404,000
- Average daily flow treated: 195 million litres per day
- Contaminants removed: 57,400 kilograms of total solids per day
- Current North End Sewage Treatment Plant (NEWPCC) licencing information
- North End Sewage Treatment Plant (NEWPCC) compliance reporting
Infrastructure
- First commissioned in 1937 as a treatment plant with digestion of sludge
- Upgraded in 1964 to a conventional activated sludge plant and converted to high purity oxygen (HPO) in 1985
- Mechanical sludge dewatering (centrifuges) was added in 1990 to dewater sludge
- To meet effluent E. coli and fecal coliform limits, Ultraviolet Disinfection (UV) went into service in 2006
- A new biological process was added in 2007 to remove ammonia nitrogen that is released during sludge digestion and dewatering
South End Sewage Treatment Plant (SEWPCC)
Located at 100 Ed Spencer Drive, just south of the Perimeter Highway, the South End Sewage Treatment Plant (SEWPCC) processes approximately 20% of the wastewater generated in the City of Winnipeg.
Plant Summary
- Population served: 176, 000
- Average daily flow treated: 58 million litres per day
- Contaminants removed: 16,780 kilograms Total Solids per day
- Current South End Sewage Treatment Plant (SEWPCC) licencing information
- South End Sewage Treatment Plant (SEWPCC) compliance reporting
Infrastructure
- Commissioned in 1974, the South End Sewage Treatment Plant (SEWPCC) was Canada’s first plant that utilizes more than 90% pure oxygen in its biological reactors
- Two biological reactors and one final clarifier were added in a 1990 plant upgrade
- In 2000, Ultraviolet Disinfection (UV) was added to meet the E.coli limit
- A thermal oxidizer was added in 2005 to reduce odor emissions from the sludge holding tanks
- Sludge (waste activated sludge and primary sludge) is sent to the North End Sewage Treatment Plant (NEWPCC) for digestion and dewatering
Odour Control Measures FAQs
What does the City do to control odour at South End Water Treatment Plant (SEWPCC)?
The heat, ventilation and air conditioning (HVAC) system takes air from a variety of different process areas at the South End Water Treatment Plant (SEWPCC), and ventilates it to an odour control stack at the facility.
The odour control stack is 45 meters high and disperses the exhaust air into the atmosphere, diluting any odorous gases.
To further reduce potential odour concerns, a thermal oxidizer unit was installed in 2005/2006. The unit treats odours coming from the sludge storage tank and truck-hauling bays. The system operates during warm weather season, from early May to late October.
Are there any changes or additional odour control measures being done as part of the current South End Water Treatment Plant (SEWPCC) Upgrade Project?
In addition to the odour control stack and the thermal oxidizer unit, a new bio-filter system will be added to the facility, as part of the South End Water Treatment Plant (SEWPCC) Upgrade and Expansion Capital project. Concentrated foul air sources from the new sludge thickening system and new sludge fermenters will be sent to the new biofilter for treatment. Biofiltration is a biological process that converts odour-causing compounds into non-odorous gases and salts. The biofilter system will be housed in a concrete enclosure.
What factors affect odour in our neighbourhoods?
There are a number of factors that may impact what we smell in our neighbourhood. Some of these include seasonal variations like precipitation, wind, and humidity. These all impact what we smell at a given time. Odours may also be the result of the treatment plant, local farmers' fields with freshly spread fertilizer or other industrial operations in our neighbourhoods. The odours that come from these places can be easily confused, making it difficult to pinpoint its origin.
The City's sewage treatment plant upgrades include industry standard odour control technology for the new process areas, which will help us minimize the plant's potential impact on the communities nearby.
Who do I notify about odour coming from the plant?
If you notice odour coming from the South End Water Treatment Plant (SEWPCC), please report it by contacting 311.
West End Sewage Treatment Plant (WEWPCC)
The West End Sewage Treatment Plant (WEWPCC) is located at 7740 Wilkes Avenue just west of the Perimeter Highway. The WEWPCC treats about 10% of the wastewater generated in the City of Winnipeg.
Plant Summary
- Population served: 86,000
- Average daily flow treated: 20 million litres per day
- Contaminants removed: 6,055 kilograms of solids per day
- West End Sewage Treatment Plant (WEWPCC) licence
- West End Sewage Treatment Plant (WEWPCC) compliance reporting
Infrastructure
- Five lagoon cells (three primary and two secondary) were put into service in 1964 and provided a treatment capacity of 14 million litres per day
- In 1973, an extended aeration plant was added to increase total treatment capacity up to 41 million litres per day
- A conventional activated sludge plant, that increased treatment capacity to 54 million litres per day, was commissioned in 1993
- In 2005, the five lagoon cells were modified to enable year-round operation to provide natural light disinfection in the summer and cooling in the winter
- The conventional activated sludge plant was modified in 2008 to remove both nitrogen and phosphorus.