Fermor Avenue Reconstruction & Widening Project - Lagimodière Boulevard to Plessis Road
This project is now complete
Ce projet est terminé
Fermor Avenue is part of the Trans-Canada Highway and a major transportation corridor in southeast Winnipeg with traffic volumes in the range of 70,000 vehicles per day. The section of Fermor Avenue between Lagimodière Boulevard to Plessis Road is in poor condition and needs to be reconstructed and widened. This is a two-year project and includes construction work in both 2019 and 2020. During construction, one lane of traffic in each direction will remain open on Fermor Avenue and intersecting streets, and access to businesses will be maintained.
With traffic reduced to one lane in each direction, motorists should expect significant delays, and are advised to allow additional travel time to get to their destinations, and use alternate routes as required. Motorists are encouraged to download and use the Waze app or real-time traffic and incident updates as well as traffic re-route options.
The project is expected to be completed late in 2020.
- Updates
- Documents
- Maps
Updates
August 18, 2020 – The intersection of Fermor and Lagimodiere will be closed August 21-23, 2020 to accommodate paving work. Fermor between Westmount Drive/Beaverhill Boulevard and Niakwa Road East will be closed to traffic except for right-hand turning yields in both the east and westbound directions. One lane of each northbound and southbound Lagimodiere will remain open; however drivers should expect significant delays, choose alternate routes, and allow additional travel time.
Traffic will be reopened as normal for the morning rush on Monday, August 24.
May 13, 2020 - Construction on Fermor Avenue from Lagimodiere Boulevard to Plessis Road is underway. Traffic on Fermor Avenue will be reduced to one lane in each direction until October 2020.
The work in 2020 will include:
- Asphalt Reconstruction of Westbound Lanes
- New path construction
- Completion of Median and Ditch Work
- Completion of final Asphalt on Eastbound Lanes
- Asphalt resurfacing of Lagimodiere Boulevard and Fermor Avenue
June 2019 - Construction on Fermor Avenue between Lagimodière Boulevard to Plessis Road is underway in the eastbound lanes. Traffic on Fermor will be reduced to one lane in each direction until November 2019.
The work in 2019 on the eastbound lanes and will include:
- Road rehabilitation
- Installation of land drainage systems and culverts
- New path construction
- Connection of Royal Mint Drive to Fermor Avenue
- Widening of the existing Fermor right-of-way
- Reconstruction of the roadway with asphalt pavement.
Documents
Document Name | Date | Type |
---|---|---|
Construction notice 1 | 2019-04-05 | Community letter |
News Release | 2019-05-17 | News release |
Construction notice 2 | 2019-05-31 | Community letter |
Final Layout | 2019-06-17 | Map |
Construction notice 3 | 2020-05-11 | Community letter |
Active Transportation Connections | 2020-07-07 | Map |
Construction notice 4 | 2020-08-18 | Community letter |