Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on November 28, 2025 @ 3:00 PM)
+
Abinojii Mikanah (WB) - Dakota St / St Marys Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Bayview Pl - Paulley Dr / McMeans Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
Bury St - Whyte Av / Irysh Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
July 14, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Chatham Pl - Morningside Dr / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 11, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Dzyndra Cr - Hatcher Rd / Bournais Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
East Gate - Blanchard Av / Middle Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Tetra Tech
Document
+
Elgin Av - Isabel St / Sherbrook St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Ghent Cv - Mayfield Cr / Mayfield Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 2, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
+
Hector Av E - Lilac St / Wentworth St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Fall 2025
Estimated to end
Summer 2026
Approx. % completed
10
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Hector Av W - Wentworth St / Stafford St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Fall 2025
Estimated to end
Summer 2026
Approx. % completed
10
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Irysh Av - Bury St / Blake St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 14, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Kate St - Elgin Av / William Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 21,2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Marcus Pl - Whiteway Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 18, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Marshall Cr - Waller Av / Clarence Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 30, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
McFarlane St N - Rover Av / Sutherland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 15, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
KGS Group
Contractor
JC Paving
Document
+
McMicken St - Sargent Av / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
+
McMullen Cr - Hatcher Rd / Hatcher Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Middle Gate - Cornish Av / East Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
Tetra Tech
Document
Facility type
Bridge
Type of work
Maintenance
Estimated to start
August 2025
Estimated to end
Summer 2026
Approx. % completed
80
Document
+
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2025
Estimated to end
Fall 2027
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2025
Estimated to end
Fall 2025
Approx. % completed
Planned
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
Barnes and Duncan
Document
+
Osborne St - Baltimore Rd / Rosedale Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
+
Osborne St/Nassau St S - Kylemore Av/Walker Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Osborne St/Nassau St S - Walker Av/Rathgar Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Paulley Dr - Redonda St / Dowling Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
Pembina Highway Bridge over Abinojii Mikanah Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Pembina Hw SB to Abinojii Mikanah EB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Pembina Hw SB to Abinojii Mikanah WB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Portage Av - Banting Dr / Sturgeon Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Portage Av - David St / Cavalier Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Portage Av - Sturgeon Rd / Cavalier Dr
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Qu'Appelle Av - Balmoral St / Kennedy St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
+
Rupert Av - Martha St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Sargent Av - Balmoral St / Edmonton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av - Furby St / Balmoral St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sims Cr - Hatcher Rd / Hatcher Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
University Cr - 80m North of Dysart Rd/Thatcher Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
University Cr - Markham Rd / 80m North of Dysart Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
West Gate - Blanchard Av / Middle Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
Tetra Tech
Document
+
Whiteway Rd - Clouston Dr / Sanford Fleming Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 18, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Whyte Av - East of Vine St / Quelch St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 8, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Whyte Av - Quelch St / Bury St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 8, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.