Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on June 6, 2023 @ 8:00 PM)
 
 


Academy Rd - Renfrew St / Wellington Cr S   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Academy Road.pdf
Agate By - Drake Bv / Drake Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Ainsworth Pl - Kirkbridge Dr / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Albina Wy/Raber Rd - Kairistine Ln/Hume St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 17, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Construction Notice_Hume Street_Kairistine Lane Alley.pdf
Alexander Av - Lily St / Martha St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Alwood Cr - Egesz St / Egesz St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 15, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Alwood Cr.pdf
Ansell Ct - Fernbank Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Ansell Court.pdf
Archibald St - Messier St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end October 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Document
2023 Construction Notice_Archibald2.pdf
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end October 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Document
2023 Construction Notice_Archibald2.pdf
Argyle St - Waterfront Dr / George Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Argyle Street.pdf
Arthur St - Notre Dame Av / McDermot Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Arthur St Sidewalk.pdf
Ash St - Wellington Cr / Academy Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Assiniboine Av - Navy Wy / Hargrave St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 15, 2023
Estimated to end July 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Construction Notice_Assiniboine Ave.pdf
Atlantic Av- Main St/Salter St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Audubon Pl - Lake Grove By / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Baden Ct - Fernbank Av/End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Baden Court.pdf
Bairdmore Bv - Service Road 832/910   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Balmoral St - Ellice Av / 458 Balmoral St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Balmoral St Sidewalk Renewal.pdf
Baltimore Rd - Casey St / Hay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Baltimore Rd - Fisher St / Casey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Beaulynn Cv - Allendale Dr / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beaumont St - Waterford By (S leg) / McGillivray Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Beaumont St.pdf
Beecher Av - Ferrier St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Global Homes
Beechtree Cr - Beliveau Rd / Beliveau Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 22, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Beechtree Cr.pdf
Beghin Av - De Baets St / Paquin Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Beghin.pdf
Beliveau Rd E - Marlene St / St Annes Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 8,2023
Estimated to end Early June 2023
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Beliveau.pdf
Bell Av - Harkness St/End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Bell Avenue.pdf
Benbow Rd - Egesz St / Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Benbow.pdf
Bentall St - Mountain Av / Redwood Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 29, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Bentall St.pdf
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 9, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2023 Construction Notice_Birchdale_Lawndale Alley.pdf
Biscayne By - McGillivray Pl / McGillivray Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 5, 2022
Estimated to end Spring 2023
Approx. % completed 90
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Biscayne Bay Construction Deferral.pdf
Bison Dr - 75m West of Pembina Hw / Markham Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Bluewater Cr - Cherwell Rd / Cherwell Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 22, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Bluewater Cr.pdf
Briar Cliff By - Killarney Av / Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 8, 2022
Estimated to end Late May 2023
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Briarcliff.pdf
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Additional information Click here
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Additional information Click here
Document
2023 Preconstruction Notice_Broadway Eastbound.pdf
Broadway - Spence St / Sherbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end October 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Broadway.pdf
Broadway/Sara Av - Sherbrook St/Maryland St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Preconstruction Notice_Alley_Broadway,Maryland Street,Sherbrook Street,Sara Avenue.pdf
Bronx Av - Brazier St / Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Bronx.pdf
Bronx Av - Roch St / Brazier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Bronx.pdf
Brookhaven By - Lakewood Bv/Lakewood Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Brotman By - John Forsyth Rd / John Forsyth Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 22, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Brotman By.pdf
Bunting St - Inkster Bv / Church Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 15, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Bunting St.pdf
Burrows Av - Aikins St / Charles St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 5, 2023
Estimated to end Early July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Burrows Ave.pdf
Byng Pl/Windermere Av - Riverside Dr/Pembina Hw   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Late May 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Backlane_Pembina to Riverside.pdf
Carlyle By - Westwood Dr / Westwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Carlyle Bay.pdf
Cass St - Musgrove St / Barker Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Chancellor Dr - Augusta Dr / Markham Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Chancellor Dr - Augusta Dr / Quincy By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 1,2023
Estimated to end Early June 2023
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Chancellor.pdf
Chancellor Dr - Lakepointe Rd / Augusta Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Channing St - Wendon By / Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Channing.pdf
Charter Dr - Benbow Rd / Egesz St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 31, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Charter Drive.pdf
Cherwell Rd - Beaverhill Bv / Bluewater Cr N leg   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Clare Av - Eccles St / Fisher St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Clare Av - Fisher St / Casey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Clerkenwell By - Aldgate Rd/Aldgate Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
College Av - Salter St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_College Ave.pdf
Collegiate St - St Matthews Av / Silver Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Collegiate Street.pdf
Consulate Rd - Ambassador Rw / Diplomat Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Consulate Road.pdf
Creek Bend Road Bridge Replacement   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cumberland Av/Sargent Av - Furby St/Sherbrook St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Preconstruction Notice_Alley_Sherbrook Street,Cumberland Avenue,Sargent Avenue,Furby Street.pdf
Cuthbertson Av - Park Bv N / Bower Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Dagmar St - Bannatyne Av / McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Dagmar Street.pdf
Dagmar St - William Av / Bannatyne Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Dagmar Street.pdf
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Darling St - Oakwood Av / Baltimore Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Day St - New AT Asphalt Path   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start August 17, 2022
Estimated to end Summer 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2022_Construction Notice_Day Street_Transcona Trail to McMeans Av E_AT Path.pdf
De La Cathedrale Av/Hamel Av - Des Meurons St/De La Morenie St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Preconstruction Notice_Alley_Cathedrale Avenue,De La Morenie Street,Des Meurons Street,Hamel Avenue.pdf
De Leglise Av - Campeau St / Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 30, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_De Leglise.pdf
De Leglise Av - St Pierre St / Campeau St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Deepwood Cv - Fernbank Av / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Deepwood Cove.pdf
Des Meurons St - Goulet St / Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end October 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Construction Notice_Des Meurons St.pdf
Dorset St - Manitoba Av / Pritchard Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Dorset Street.pdf
Dowker Av/Fletcher Cr - Fletcher Cr/Pembina Hw   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Dugald Rd - Panet Rd / Dawson Rd N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Dugald.pdf
Dunkirk Pl - Kingston Rw / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Eccles St - Arnold Av / Morley Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Edmonton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Ellice Av - Colony St / Kennedy St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Ellice Ave.pdf
Empress Pathway   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Empress Street.pdf
Erin St - Notre Dame Ave / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 1, 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2023 Construction Notice_Erin St.pdf
Erin St - Sargent Av / Wolever Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 24,2022
Estimated to end Fall 2023
Approx. % completed 40
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2022 Construction Notice_Erin.pdf
Exmouth Bv - Aldershot Bv / Holdsworth Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Exmouth Boulevard.pdf
Fairlane Av - Isbister St / Buchanan Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Fairlane Avenue.pdf
Fallbrook By - Pebble Beach Rd / Pebble Beach Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fernwood Av - St Annes Rd / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 17, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Fernwood Ave.pdf
Fifth Av/Guay Av - Des Meurons St/St Marys Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Figaro St - Herbert Av / Talbot Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Figaro Street.pdf
Fisher St - Arnold Av / Morley Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Fisher St - Montgomery Av / Churchill Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Fisher St - Morley Av / Oakwood Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Flamingo Av- Athlone Dr/Sturgeon Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Foster St - Manhattan Av/Beach Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Foster Street.pdf
Furby St - Portage Av / Broadway   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Furby Street.pdf
Galt Av - Duncan St / Lily St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Galt Avenue.pdf
Garden Grove Dr - Fairgrove By / Fairgrove By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Garden Grove.pdf
Gatineau By - Crestwood Cr / Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Gaynor Pl - Alwood Cr / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 15, 2023
Estimated to end Mid June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Gaynor Pl.pdf
Glenthorne Cr - Greendell Av / Darwin St   View Map
Facility type Street
Type of work TBO
Estimated to start June 7, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Glenthorne Cr2.pdf
Glenthorne Cr - Woodlawn Av / Greendell Av   View Map
Facility type Street
Type of work TBO
Estimated to start June 7, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Glenthorne Cr1.pdf
Goulet St - Traverse Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end October 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Additional information Click here
Document
2023 Construction Notice_Goulet St.pdf
Grandmont Bv - Co Op Entrance/ 40m West   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Grandmont Bv - Delorme By / East P/L of 96 Grandmont Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Grandmont Bv - Gravel Pathway / Delorme Pl   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Grandmont Bv - Le Maire St / Retention Pond   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Grant Av - 150m East of Kenaston / Borebank St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Document
2022 Construction Notice_Grant Ave.pdf
Grant Av - Borebank St / Montrose St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Late August 2023
Approx. % completed 80
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2023 Construction Notice_Grant Ave.pdf
Grassie Bv - Lagimodiere Bv / Molson St   View Map
Facility type Street
Type of work Reconstruction
Greencrest Av - Ulster St / Pembina Hw   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Greenwood Pl - Portage Av / Wolseley Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Greenwood Place.pdf
Groverdale Av - Burdick Pl / Garden Grove Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Groverdale.pdf
Harbourview Park Pathway   View Map
Facility type Park
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Harbourview Park.pdf
Harrogate By - Hunterspoint Rd / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harrow St - Academy Rd / Dromore Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Harrow St - Academy Rd / Kingsway   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Hartford Av - CPR Winnipeg Beach / Montcalm Cr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 5, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Hartford Ave.pdf
Hartford Av - Main St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Fall 2024
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Hartford Av - McGregor St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Fall 2024
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Hartford Av - Sinclair St / Montcalm Cr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 5, 2023
Estimated to end Mid July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Hartford Ave.pdf
Harvest Ln - Valley View Dr / Heritage Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hayes St - Whiteshell Av / McMeans Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Hayes Street.pdf
Hazel Dell Av - Brazier St / Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Hazel Dell.pdf
Heaton Av - Waterfront Dr / Argyle St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Heaton Avenue.pdf
Helmsdale Av - Brazier St / Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Helmsdale.pdf
Herbert Av - Figaro St / Chester St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Herbert Avenue.pdf
Holdsworth Av - Glastonbury Bv / Aldershot Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Holdsworth Avenue.pdf
Horace St - Des Meurons St / Enfield Cr   View Map
Facility type Street
Type of work TBO
Estimated to start May 8, 2023
Estimated to end Late May 2023
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Horace St.pdf
Horace St - Youville St / Des Meurons St   View Map
Facility type Street
Type of work TBO
Estimated to start May 8, 2023
Estimated to end Late May 2023
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Horace St.pdf
Horetzky St - Sanford Fleming Rd / Meadow Gate Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Horetzky Street.pdf
Inkster Bv - McKenzie St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jackson Av- Stafford St/Harrow St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Jewett By - Sinnott St / Sinnott St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 26, 2022
Estimated to end Spring 2023
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Jewett Bay Construction Deferral.pdf
Johnson Av W - Levis St / Henderson Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Additional information Click here
Jubilee Av - Cockburn St S / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Late October 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2023 Construction Notice_Jubilee Ave.pdf
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 9, 2023
Estimated to end Mid August 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving
Document
2023 Construction Notice_Kavanagh_Giroux Alley.pdf
Keewatin St - Burrows Av/Gallagher Av W   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start To Be Determined
Estimated to end To Be Determined
King Edward St and Park Lane Av Sidewalk (East Side)   View Map
Facility type Sidewalk
Type of work New Construction
Estimated to start May 15, 2023
Estimated to end Mid June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Park Lane Ave.pdf
King Edward St and Park Lane Av Sidewalk (East Side)   View Map
Facility type Sidewalk
Type of work New Construction
Estimated to start May 15, 2023
Estimated to end Mid June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Park Lane Ave.pdf
Kirby Dr - Ness Av / Setter St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
La Barriere St - De Leglise Av / St Therese Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
La Grave St - Lemay Av / Lord Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 30, 2023
Estimated to end Mid June 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_La Grave.pdf
Lagimodiere Bv - Fermor Av / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Lagimodiere Bv - Island Shore Bv / Lagimodiere Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Bishop Grandin Boulevard.pdf
Lagimodiere Bv - Warman Rd/Dugald Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Lake Green Pl - Lake Lindero Rd / Lake Lindero Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lake Linnet Pl - Lake Lindero Rd / Lake Lindero Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Lakeshore.pdf
Lakeshore Rd - Chancellor Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 5, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Lakeshore Frontage.pdf
Langside St - Cumberland Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end August 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Construction Notice_Langside St.pdf
Larche Av W - Winona St / Transcona Trail   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Fall 2023
Consultant WSP Canada Inc
Larkin Cv - Brentlawn Bv / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Le Maire St - Grandmont Bv / Hydrant   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Linacre Rd - Radcliffe Rd / Michigan Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Linden Av - Brazier St / Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Linden.pdf
Linden Av - Roch St / Brazier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Linden.pdf
Logan Av - Blake St/Vine St   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av - Dee St / Keewatin St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Tetra Tech
Document
2023 Construction Notice_Logan.pdf
Logan Av - Disraeli Fwy / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Lumsden Av - Lake Ridge Rd / Cavalier Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Lumsden Avenue.pdf
Lyndale Drive Erosion Protection and Pathway Upgrades - Highfield St/Birchdale Ave   View Map
Facility type Pedestrian / Cycling
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Macalester By - Silverstone Av / Silverstone Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
MacDonald Av - Gomez St / Waterfront Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_MacDonald Avenue.pdf
Machray Av - Salter St / Powers St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Machray Ave.pdf
Madrigal Cs - Marquis Cr/Mapleton Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Madrigal Close.pdf
Magdalene By - Baylor Av / Baylor Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Manahan Av - Pembina Hw / Hudson St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Manahan Ave.pdf
Mandan Rd - Herron Rd / Mariner Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Mandan Road.pdf
Maplegrove Rd - Maplegrove Rd / Maplegrove Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Maplegrove.pdf
Markham Rd - Chancellor Dr (E) / Forest Lake Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Mazenod Rd - De Baets St / Dugald Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Mazenod.pdf
Mazenod Rd - Dugald Rd / Paquin Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Mazenod.pdf
McDermot Av - McPhillips St / Myrtle St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_McDermot Avenue.pdf
McGregor St - Church Av / Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McGregor St - Seven Oaks Av / McAdam Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
McMicken St - Cumberland Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Preconstruction Notice_McMicken Street.pdf
McMillan Av/Corydon Av/Donald St   View Map
Facility type Street
Type of work Preservation
Estimated to start Early September 2022
Estimated to end Summer 2023
Approx. % completed 50
Consultant City Of Winnipeg - Streets Maintenance Division
Document
2022_Construction Notice_Donald Street.pdf
McPhillips St - Machray Av / Mountain Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Document
2022_Construction Advance Notice_McPhillips.pdf
Midland St - Notre Dame Av / Saskatchewan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Midwinter Av - Stadacona St / 193 Midwinter Ave   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Moberly Av - Sanford Fleming Rd / Cambie Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Moberly Avenue.pdf
Moberly Av - Whiteway Rd / Sanford Fleming Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Moberly Avenue.pdf
Montrose St - Grant Av / Mathers Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Montrose St.pdf
Moore Av - Dunkirk Dr / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 1, 2022
Estimated to end Late June 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Moore.pdf
Moore Av - Flynn St / Pulberry St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 1, 2022
Estimated to end Late June 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Moore.pdf
Moore Av - Pulberry St / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 1, 2022
Estimated to end Late June 2023
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Moore.pdf
Moore Av - River Rd / Flynn St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 1, 2022
Estimated to end Late June 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Moore.pdf
Morrow Av - St Annes Rd / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 29, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Morrow Ave.pdf
Mountain Ave - Arlington St / Airlies St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 1, 2023
Estimated to end Late August 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Document
2023 Construction Notice_Mountain Avenue.pdf
Musgrove St - Cass St / Barker Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Niakwa Trail Pathway   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Niakwa Trail.pdf
Niakwa Trail Pathway   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Niakwa Trail.pdf
Niakwa Trail Pathway   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Niakwa Trail.pdf
Norfolk Av - Kingston Rw / Oakcrest Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Northwest Hydro Corridor Pathway - Leila Av / Church Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 14, 2022
Estimated to end Spring 2023
Approx. % completed 80
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Northwest Hydro New Multi-Use Pathway.pdf
Norwood & Main Street Bridge Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Notre Dame St - Langevin St / St Joseph St   View Map
Facility type Street
Type of work TBO
Estimated to start May 8, 2023
Estimated to end Late May 2023
Approx. % completed 5
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_Notre Dame.pdf
Nugent Rd - Hatcher Rd / Rougeau Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Nugent Road.pdf
Oakcrest Pl - End / Dunkirk Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Oakdale Dr - Coy Av / Grant Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Oakenwald Av - Wicklow St / Pembina Hw   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Oakview Av - Brazier St / Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Oakview.pdf
Oakwood Av - Eccles St / Darling St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Osborne St - Stradbrook Av / Wardlaw Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Pacific Av - Arlington St / Xante St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Pacific Avenue.pdf
Pacific Av - Xante St / McPhillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Pacific Avenue.pdf
Palmerston Av - Arlington St / Ethelbert St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Mid August 2023
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Construction Notice_Palmerston Avenue.pdf
Pandora Av E - 645 Pandora Av E / Wayoata St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Pandora Av E - Brelade St / 645 Pandora Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Pandora Av E - Ravenhurst St / Brelade St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Pandora Ave E - Redonda St / Wayoata St   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start July 4, 2022
Estimated to end Summer 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Construction Notice_Pandora Ave_Wayoata St to Redonda St_AT Path.pdf
Panet Rd - Abandoned Railway X-ing / Marion St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Panet.pdf
Panet Rd - Dugald Rd/ Abandoned Railway X-ing   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Panet.pdf
Panet Rd - Regent Av W / Mission St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Panet.pdf
Panet Rd Pathway - Reenders Dr/Talbot Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 26, 2022
Estimated to end Summer 2023
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Reenders Dr.pdf
Peake Av - Robson St / Plessis Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Peake Avenue.pdf
Pembina Hw - McGillivray Bv / Chevrier Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 8, 2023
Estimated to end Late October 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2023 Construction Notice_Pembina.pdf
Pipeline Rd - North of Templeton Av to South of Storie Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 1, 2023
Estimated to end Late June 2023
Plessis Rd - Devonshire Dr / Gunn Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start May 15,2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Construction Notice_NB Plessis Road.pdf
Powers St - Cathedral Av / Machray Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Powers St.pdf
Pritchard Av - Chudley St / Keewatin St   View Map
Facility type Street
Type of work TBO
Estimated to start June 5, 2023
Estimated to end Early July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Pritchard.pdf
Pritchard Av - Main St / Charles St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 5, 2023
Estimated to end Early July 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_Pritchard.pdf
Pritchard Av - Powers St / Charles St   View Map
Facility type Street
Type of work TBO
Estimated to start June 5, 2023
Estimated to end Early July 2023
Approx. % completed Planned
Document
2023 Construction Notice_Pritchard.pdf
Pritchard Av - Powers St / McKenzie St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 5, 2023
Estimated to end Early July 2023
Approx. % completed Planned
Document
2023 Construction Notice_Pritchard.pdf
Radburn Pl - End / Beaverhill Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Raleigh St - Glenway Av / Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Raleigh.pdf
Ravine Dr - River Pointe Dr / Settlers Rd   View Map
Facility type Street
Type of work TBO
Estimated to start May 10, 2023
Estimated to end Early June 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2023 Construction Notice_ Ravine.pdf
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 2022
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group Limited
Document
2022 Preconstruction Notice_Redwood Ave.pdf
Reenders Pathway - Stapon Rd/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 26, 2022
Estimated to end Summer 2023
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Reenders Dr.pdf
Reenders Pathway - Stapon Rd/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start September 26, 2022
Estimated to end Summer 2023
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Document
2022_Construction Notice_Reenders Dr.pdf
Refinery District BRT Pathway Connection   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Refinery District BRT.pdf
Regal Av - Des Meurons St / St Annes Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 17, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Regal Ave.pdf
Renfrew St - Grant Av / Taylor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 29, 2022
Estimated to end Spring 2023
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2022_Renfrew Street Construction Deferral.pdf
Renfrew St - John Brebeuf Pl / Grant Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Renfrew St.pdf
River Av - Osborne St / Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2023
Estimated to end Late October 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2023 Preconstruction Notice_Wellington.pdf
Roblin Bv - Grant Av / William R Clement Pw   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Roblin Ave.pdf
Roblin Bv - William R Clement Pw / Roblin Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Preconstruction Notice_Roblin Ave.pdf
Ross Av - King Edward St/Oddy St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Ross Avenue West.pdf
Rossmere Cr - Dunvegan St / Kildonan Dr   View Map
Facility type Street
Type of work TBO
Estimated to start September 23, 2022
Estimated to end Summer 2023
Approx. % completed 90
Consultant KGS Group Limited
Contractor Wintec Building Services Inc.
Document
2022_Construction Notice_Rossmere Cr.pdf
Route 90 Culvert at Omand's Creek   View Map
Facility type Bridge
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed 0
Consultant Morrison Hershfield Limited
Royal Salinger Rd - Niakwa Rd / Pebble Beach Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Salter St - Jefferson Av / Inkster Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Document
2022_Construction Advance Notice_Salter.pdf
Samantha Pl - Tully Rd / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Samantha Place.pdf
Sargent Av - Balmoral St / Edmonton St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Sargent Av - Furby St / Balmoral St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Sargent Av/Ellice Av - Clifton St/Spruce St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Construction Notice_Spruce Street_Clifton Street Alley.pdf
Sargent Av/Ellice Av - Furby St/Sherbrook St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Preconstruction Notice_Alley_Sargent Avenue,Sherbrook Street,Furby Street,Ellice Avenue.pdf
Saskatchewan Av - King Edward St / Century St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Summer 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Saskatchewan Av - King Edward St / Sherwin Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 18, 2022
Estimated to end Summer 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Saskatchewan Av - Midland St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Saskatchewan Av - St James St / Border St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 18, 2022
Estimated to end Summer 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Saskatchewan Ave_Sherwin to St James.pdf
Scotland Av - Harrow St / Stafford St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Scotland Ave.pdf
Scotland Av - Harrow St / Wilton St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Scotland Ave.pdf
Scurfield Bv - Kenaston Bv / Henlow By   View Map
Facility type Sidewalk
Type of work New Facility
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Scurfield Blvd New Sidewalk.pdf
Seabrook Cv - Beaverhill Bv / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Selkirk Av - Main St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Document
2023 Preconstruction Notice_Selkirk.pdf
Selkirk Ave - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Spring 2023
Approx. % completed 90
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
Shields St - Moberly Av / Sanford Fleming Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Shields Street.pdf
Sinnott St - Barker Bv / Barker Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Sinnott Street.pdf
Smith - Graham Av/Midtown Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end July 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2023 Construction Notice_Smith.pdf
Smith St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 23, 2023
Estimated to end July 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2023 Construction Notice_Smith.pdf
Smith St - Notre Dame / Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 23, 2023
Estimated to end July 2023
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2023 Construction Notice_Smith.pdf
Smith St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 23, 2023
Estimated to end July 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Document
2023 Construction Notice_Smith.pdf
Sparrow Rd - Roblin Bv / 46 Sparrow Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Sprague St - Portage Av / Wolseley Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 5, 2023
Estimated to end August 2023
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2023 Construction Notice_Sprague St.pdf
Springfield Rd - Cox Bv / Lagimodiere Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
St Annes Rd - Hindley Av/Worthington Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2022
Estimated to end Fall 2023
Approx. % completed Planned
Document
2022 Preconstruction Notice_St Annes Rd 475.pdf
St Thomas Rd - End / Fermor Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
St Vital Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start March 1, 2023
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
St. James Bridges Minor Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Winter 2022
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Tetra Tech
St. Mary's Road Riverbank Stability   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Stafford St - Scotland Av/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2023
Estimated to end Fall 2023
Approx. % completed 10
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Sterling Lyon Pw - Victor Lewis Dr/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Sterling Lyon Pw - Victor Lewis Dr/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Stillwater Rd - Brookhaven By / Willowlake Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Stradbrook Av - Queen Elizabeth Wy/Harkness St   View Map
Facility type Street
Type of work Preservation
Estimated to start June 2023
Estimated to end August 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Stradbrook Ave.pdf
Stradbrook Ave - Wellington Cr / Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2023
Estimated to end Late October 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2023 Preconstruction Notice_Stradbrook.pdf
Summerside Av - Caledon Rd / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Tahoe By - Lakewood Bv / Lakewood Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Taylor Ave - Harrow St / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2022
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Contractor Nelson River Construction
Additional information Click here
Document
2022 Preconstruction Notice_Taylor Ave.pdf
Tulane By - Pasadena Av / Pasadena Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
University Cr - Pembina Hw / Thatcher Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 15, 2023
Estimated to end July 2023
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_University Cres.pdf
University Cr - Thatcher Dr / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end July 2023
Approx. % completed 70
Consultant AECOM Canada Ltd
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_University Cres.pdf
Victoria Av E - Roanoke St / Leola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 8, 2023
Estimated to end Early June 2023
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Document
2023 Construction Notice_Victoria Avenue E.pdf
Wall St - Wellington Av / Notre Dame Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 16,2022
Estimated to end Fall 2023
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Document
2022 Construction Notice_Wall Street.pdf
Waller Av/Clarence Av - Hudson St/Marshall Cr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 23, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2023 Construction Notice_Hudson Street.pdf
Warde Av - 337 Warde Ave / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Warde Av - Dakota St / John Forsyth Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Warde Av - John Forsyth Rd / 337 Warde Ave   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Wardlaw Av - Nassau St N / Daly St N   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Warsaw Av - Cockburn St N / Lilac St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Warsaw Av - Hugo St N / Cockburn St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Watson St - Leila Av / Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2023
Estimated to end Fall 2023
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Watson St.pdf
Waverley St - Cadboro Rd / 165m South of Cadboro Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant KGS Group
Document
2023 Preconstruction Notice_Waverley St.pdf
Wellington Ave AT Path   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_Wellington Ave.pdf
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2023
Estimated to end Late October 2023
Approx. % completed Planned
Consultant WSP Canada Inc.
Document
2023 Preconstruction Notice_River.pdf
West Fernwood Av - Bronstone Bv / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
West Fernwood Av - Bronstone Bv / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Whiteshell Av - McMeans Av W / Winona St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Whiteshell Avenue.pdf
Wildwood G Pk - South Dr / Wildwood St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Wildwood H Pk - South Dr / South Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Wilkes Av - Victor Lewis Dr/Waverley St   View Map
Facility type Street
Type of work Preservation
Estimated to start June 2023
Estimated to end August 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Wilkes Ave.pdf
Wilkes Av - Waverley St / Wilkes Av   View Map
Facility type Street
Type of work Preservation
Estimated to start June 2023
Estimated to end August 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Wilkes Ave.pdf
William Av - Arlington St / McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2022
Estimated to end Summer 2023
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
2022 Preconstruction Notice_Selkirk and William.pdf
William Av - Main St / King St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Preconstruction Notice_William Ave Sidewalk Renewal.pdf
Winona St - Larche Av W / McMeans Av W   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023_Preconstruction Notice_Winona Street.pdf
Woodchester By - Cathcart St/Cathcart St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Woodford By - Meadowood Dr / Meadowood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Wyatt Rd - Filkow By / Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 29, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Wyatt Rd.pdf
Wyatt Rd - Mandalay Dr / Filkow By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 29, 2023
Estimated to end Late July 2023
Approx. % completed Planned
Consultant WSP Canada Inc
Document
2023 Construction Notice_Wyatt Rd.pdf
Wynford Dr - St Martin Bv / Ainsdale Wy   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Wynford Dr - St Martin Bv / Ainsdale Wy   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Late June 2023
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_York Ave.pdf
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Late June 2023
Approx. % completed 0
Consultant City Of Winnipeg - Engineering Division
Document
2023 Construction Notice_York Ave.pdf
Yukon Av - Milt Stegall Dr / St James St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 24, 2022
Estimated to end Summer 2023
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2022 Construction Notice_Yukon_St James to Empress.pdf

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.