Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on November 22, 2024 @ 8:00 PM)
 
 


Abinojii Mikanah (EB) - Dakota St / St Annes Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Abinojii Mikanah (EB) - River Rd / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Abinojii Mikanah (EB) - St Marys Rd / Dakota St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Adamar Rd - Pembina Hw/End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 20, 2024
Estimated to end Late September 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice_Adamar Road_Revised.pdf
Archibald St - Messier St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Additional information Click here
Document
2024 Construction Notice_Archibald Phase3.pdf
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Additional information Click here
Document
2024 Construction Notice_Archibald Phase3.pdf
Arlington Bridge Reconstruction - Selkirk Av / McDermot Av   View Map
Facility type Bridge
Type of work Study
Estimated to start Study
Estimated to end Study
Approx. % completed Study
Additional information Click here
Assiniboine Av - Navy Wy / Hargrave St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Construction Notice_Assiniboine Ave.pdf
Augusta Dr - Chancellor Dr / Greensboro Sq   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Augusta.pdf
Augusta Dr - Chancellor Dr / Lakeside Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Augusta.pdf
Augusta Dr - Lakeside Dr / Chancellor Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Augusta.pdf
Bayshore Cv - Beaverhill Bv / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Baywater Pl - Beaverhill Bv / Beaverhill Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Beaumont St - Waterford By (S leg) / McGillivray Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Beaumont St.pdf
Beecher Av - Ferrier St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Global Homes
Bison Dr - 75m West of Pembina Hw / Markham Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Blenheim Av - Des Meurons St / St Annes Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27,2024
Estimated to end September 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice1_Blenheim Ave Reconstruction.pdf
Brady Rd - Ethan Boyer Way / Brady Road Landfill Access   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Brady Road.pdf
Bridge Lake Dr - Traffic Calming   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start September 9,2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_Bridge Lake Drive.pdf
Broadway - Osborne St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start April 29, 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Additional information Click here
Document
2024 Construction Notice_Broadway Westbound2.pdf
Broadway - Spence St / Sherbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 8, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J&D Penner Ltd
Document
2023 Construction Notice_Broadway Sidewalk Renewal.pdf
Brock St - Mathers Av / Taylor Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 24, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice1_Brock St Reconstruction.pdf
Cadiz By - Malone St / Buckle St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Cadiz.pdf
Camiel Sys St - Plessis Rd / Mazenod Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Carlyle By - Westwood Dr / Westwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 6, 2024
Estimated to end Early July, 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Darco Enterprises
Document
2024 Construction Notice2_Carlyle Bay.pdf
Carruthers Av - Cottingham St / 1037 Lansdowne Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Carruthers Av - Sinclair St / Airlies St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 23, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Carruthers Avenue.pdf
Caton St - Des Meurons St / St Marys Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Champlain St - Niverville Av / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Charles St - Machray Av / Church Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 3, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Charles St Reconstruction.pdf
Church Av - Main St / Charles St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2024
Estimated to end August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_Church Ave Reconstruction.pdf
Clare Av - Eccles St / Fisher St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Clare Av - Fisher St / Casey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Cochrane St - Inkster Bv / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 10, 2024
Estimated to end Late July, 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice1_Cochrane St Rehabilitation.pdf
Cochrane St - Lansdowne Av / Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 10, 2024
Estimated to end Late July, 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice1_Cochrane St Rehabilitation.pdf
Collegiate St - St Matthews Av / Silver Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 6, 2024
Estimated to end Early July, 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Darco Enterprises
Document
2024 Construction Notice2_Collegiate Street.pdf
Courtwood Pl - Beaverhill Bv / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Creek Bend Road Bridge Replacement   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Additional information Click here
Cumberland Av/Carlton St - Cumberland Av/Qu'Appelle Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end Fall 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Cumberland Av/Hargrave St - Cumberland Av/Ellice Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Hargrave Donald Alley.pdf
Cumberland Av/Sargent Av - Furby St/Sherbrook St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Preconstruction Notice_Alley_Sherbrook Street,Cumberland Avenue,Sargent Avenue,Furby Street.pdf
Dahlia Av - End / Sinclair St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 14, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Dahlia Avenue.pdf
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 8,2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Wintec
Document
2023 Construction Notice_Dakota St2.pdf
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 8,2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Wintec
Document
2023 Construction Notice_Dakota St2.pdf
Daly St N - Pembina Hw / Lorette Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice_Daly Street North.pdf
Day St - Pandora St / Regent Av   View Map
Facility type Pedestrian / Cycling
Type of work Rehabilitation
Estimated to start September 23, 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant Dillon Consulting Limited
Additional information Click here
Document
2024 Construction Notice_Day Street.pdf
De La Cathedrale Av/Hamel Av - Des Meurons St/De La Morenie St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Preconstruction Notice_Alley_Cathedrale Avenue,De La Morenie Street,Des Meurons Street,Hamel Avenue.pdf
Dearborn Av - Lacy St / Brazier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 70
Consultant Dillon Consulting Limited
Delorme By - Grandmont Bv / Grandmont Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Delorme Bay.pdf
Dorge Dr - Gendreau Av / Le Maire St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Dorge Drive.pdf
Dorset St - Burrows Av/Tyndall Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 21, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice2_Dorset St & Tyndall Ave Sidewalk Renewal.pdf
Du Couvent Av - Entrance Approach/St Pierre St   View Map
Facility type Sidewalk
Type of work New Facility
Estimated to start May 2024
Estimated to end June 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice1_St Pierre St-De L'Eglise St to Du Couvent Ave with FR.pdf
Dudley Av - Daly St N / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice_Dudley Avenue.pdf
Dudley Av - End / Daly St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice_Dudley Avenue.pdf
Dufferin Av - King St/Robinson St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start September 9, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_Dufferin Ave Sidewalk Rehabilitation.pdf
Dufferin Av - Robinson St/Aikins St   View Map
Facility type Sidewalk
Type of work Rehabilitation
Estimated to start September 9, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_Dufferin Ave Sidewalk Reconstruction.pdf
Dugald Rd (EB) - Ravenhurst St / 390m east of Ravenhurst St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 9,2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Document
2024 Construction Notice_Dugald Rd.pdf
Dumoulin St - Thibault St / Langevin St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Dunkirk Dr - Dunkirk Dr / Kingston Rw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - St Vital Bridge / Norberry Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - Kingston Rw / Dunkirk Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Dr - St Vital Rd / St Vital Bridge   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Dunkirk Pl - Kingston Rw / End   View Map
Facility type Street
Type of work TBO
Estimated to start July 24, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Document
2023 Construction Notice_Dunkirk Place.pdf
Dunraven Av - Overton St / St Marys Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 3, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice_Dunraven Avenue Reconstruction.pdf
Edderton Av - Derek St / Beaumont St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 13, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice2_Edderton Ave Reconstruction.pdf
Edderton By - Beaumont St / End   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start August 12, 2024
Estimated to end Mid September 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice_Edderton Bay3.pdf
Egerton Rd - Morier Av / South End   View Map
Facility type Street
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Egerton Road.pdf
Eldridge Av - Elmhurst Rd / Haney St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Eldridge Ave.pdf
Ellice Av - Ashburn St / Strathcona St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Document
2024 Construction Notice_Ellice_Revised.pdf
Ellice Av - Erin St / Ashburn St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Document
2024 Construction Notice_Ellice_Revised.pdf
Ellice Av - Strathcona St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2024
Estimated to end Summer 2025
Approx. % completed 90
Consultant WSP Canada Inc
Document
2024 Construction Notice_Ellice_Revised.pdf
Fairlane Av - Isbister St / Buchanan Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 6, 2024
Estimated to end Early July, 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Darco Enterprises
Document
2024 Construction Notice2_Fairlane Avenue.pdf
Fisher St - Arnold Av / Morley Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Oakwood Ave to Arnold Ave.pdf
Fisher St - Montgomery Av / Churchill Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Montgomery Ave to Churchill Drive.pdf
Fisher St - Morley Av / Oakwood Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Oakwood Ave to Arnold Ave.pdf
Fleetwood Rd - #4 / #28   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Fleetwood Road 4 to 28.pdf
Fleetwood Rd - #82 / #122   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Fleetwood Road 82 to 122.pdf
Fortier Av - Summerfield Wy / Pentland St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Fortier Ave.pdf
Fowler St/Main St - Anderson Av/St Johns Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 2024
Estimated to end August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_Alley-St Johns_Anderson Reconstruction.pdf
Freemont By - Fairlane Av / Fairlane Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Freemont.pdf
Furby St - McDermot Av / Notre Dame Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 22, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Furby St (William) Rehabilitation.docx.pdf
Furby St - William Av / Bannatyne Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 22, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Furby St (McDermot) Rehabilitation.pdf
Gerrond By - Cavalier Dr / Cavalier Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant KGS Group
Document
2024 Construction Notice1_Gerrond.pdf
Ghent Cv - Mayfield Cr / Mayfield Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Ghent Cove.pdf
Gibraltar By - Normandy Dr / Normandy Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant KGS Group
Document
2024 Construction Notice1_Gibraltar.pdf
Golspie St - Munroe Av / Watt St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 26, 2024
Estimated to end Early August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice1_Golspie St Rehabilitation.pdf
Gordon Av - Stadacona St / Brazier St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant Dillon Consulting Limited
Goulet St - Traverse Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2023 Construction Notice_Goulet St.pdf
Grant Av (EB) - Rockwood St / Wilton St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Grant Ave.pdf
Grant Av (EB) - Wilton St / Stafford St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Grant Ave.pdf
Grant Av (WB) - Stafford St / Harrow St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Grant Ave.pdf
Green Valley By - Louelda St / Louelda St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Greensboro By - Chancellor Dr / Augusta Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Greensboro Bay.pdf
Greensboro Sq - Greensboro By / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Greensboro Square.pdf
Gunnell St - Logan Av / Alexander Av   View Map
Facility type Street
Type of work TBO
Estimated to start June 17, 2024
Estimated to end Early July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Gunnell St.pdf
Haggart Av - Meridian Dr / 195 Haggart Av   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Harrow St - Harrow St E / Sparling Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Preconstruction Notice1_Harrow Sparling.pdf
Harrow St - Taylor Av / Pembina Hw   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Hartford Av - Main St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice2_Hartford Av - McGregor to Main.pdf
Hartford Av - McGregor St / Salter St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 19, 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice3_Hartford Av - McGregor to Main.pdf
Hood Av - Scarfe St / Leahcrest Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 14, 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Hood Avenue.pdf
Howard Kendel Pl - McLellan Dr / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2, 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Howard Kendel Place.pdf
Inkster Bv (EB) - Andrews St / Salter St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Inkster Bv (EB) - Fife St / Lansdowne Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Fife to McPhillips.pdf
Inkster Bv (EB) - Lansdowne Av / McPhillips St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Fife to McPhillips.pdf
Inkster Bv (EB) - McGregor St / Andrews St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2025
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Inkster Bv (EB) - McKenzie St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2025
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Inkster Bv (EB) - McKenzie St / McGregor St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Inkster Bv (EB) - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Inkster Bv (EB) - Sheppard St / Milner St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sheppard to Milner.pdf
Inkster Bv (EB) - Sinclair St / Arlington St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Nelson River Construction
Document
2024 Construction Notice1_Inkster Blvd-Sinclair to Main.pdf
Irene St - Sony Pl / Waller Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Summer 2025
Approx. % completed 20
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice1_Irene Street.pdf
Irene St - Waller Av / Clarence Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27, 2024
Estimated to end Mid September 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice1_Irene Street.pdf
Jubilee Av - Cockburn St S / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2023 Construction Notice_Jubilee Ave.pdf
Kanata St - Ravelston Av E / Regent Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Kanata St - Regent Av E / Pandora Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Keewatin St - Burrows Av/Gallagher Av W   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 90
Kern Dr - Roanoke St / Kanata St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Kingston Rw - Dunkirk Dr / Dunkirk Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Kullman St - Snowdon Av / Kimberly Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Lacy St - Gordon Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Lagimodiere Bv - 145m North of Sage Creek Bv / Bishop Grandin Bv   View Map
Facility type Street
Type of work Mill & Fill
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Lagimodiere Bv - Bishop Grandin Bv / Fermor Av   View Map
Facility type Street
Type of work Mill & Fill
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Lagimodiere Bv - Fermor Av / Cottonwood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Wintec
Document
2023 Construction Notice_Lagimodiere Blvd.pdf
Lagimodiere Bv - Warman Rd/Dugald Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Langside St - Cumberland Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Construction Notice_Langside St.pdf
Lansdowne Av - St Cross St / Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 10, 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice1_Lansdowne Ave Rehabilitation.pdf
Lenore St/Ruby St - Preston Av/Westminster Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start June 26, 2024
Estimated to end Mid September 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice1_Ruby St Lenore St Alley.pdf
Lilian Av - Poulin Pl / Cromwell St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Linwood St - Bruce Av/Portage Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Linwood St - Ness Av/Bruce Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lipton St - Portage Av / Westminster Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Lipton St Palmerston to Westminster.pdf
Lipton St - Westminster Av / Wolseley Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Lipton St Palmerston to Westminster.pdf
Lipton St - Wolseley Av / Palmerston Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Lipton St Palmerston to Westminster.pdf
Lismore Av - Oddy St / King Edward St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 3, 2024
Estimated to end Early July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Lismore Ave Rehabilitation.pdf
Logan Av - Blake St/Vine St (Rail Crossing)   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Lorette Av - Daly St N / Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice_Lorette Avenue.pdf
Luxton Av - End / Scotia St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 21,2024
Estimated to end Early August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Luxton Ave Reconstruction.pdf
Luxton Av - Scotia St / St Cross St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 2024
Estimated to end August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Luxton Ave Reconstruction.pdf
Machray Av - Main St / Aikins St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice1_Machray Ave Reconstruction.pdf
Manahan Av - Pembina Hw / Hudson St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 31, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_Manahan Ave.pdf
Mazenod Rd - De Baets St / Camiel Sys St   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
McAdam Av (EB) - End / Scotia St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 21,2024
Estimated to end Early August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_McAdam Ave Rehabilitation.pdf
McAdam Av (WB) - Scotia St / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2024
Estimated to end August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_McAdam Ave Rehabilitation.pdf
McAdam Av - Lane / Sinclair St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant Dillon Consulting Limited
McGregor St (NB) - Partridge Av / Leila Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St (SB) - Leila Av / Partridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St - Alley South of Partridge Av / Kingsbury Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St - Burrin Av / Jefferson Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St - Jefferson Av / Seven Oaks Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St - Kingsbury Av / Burrin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McGregor St - Partridge Av/ Alley South of Partridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 13, 2024
Estimated to end Late October 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
McMahon Pl - McLellan Dr / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 2, 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_ McMahon Place.pdf
McMicken St - Cumberland Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Preconstruction Notice_McMicken Street.pdf
Melrose Av E - Leola St / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant Dillon Consulting Limited
Meridian Dr - Discovery Pl / Inksbrook Dr   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Midland St - Notre Dame Av / Saskatchewan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 6,2024
Estimated to end Late September 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Midland and Sask.pdf
Moberly Av - Sanford Fleming Rd / Cambie Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 21, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_Moberly Avenue.pdf
Montclair By - Lakeshore Rd / Lakeshore Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Montclair Bay.pdf
Montgomery Av - Fisher St / Casey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant KGS Group
Document
2024 Construction Notice1_Montgomery Av.pdf
Montrose St - Grant Av / Mathers Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Montrose St.pdf
Moray Street Bridge Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Mount Auburn By - Garton Av / Garton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 24, 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice1_Mount Auburn Bay Rehabilitation-TBO.pdf
Nassau St S - Jubilee Av / McNaughton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant KGS Group
Document
2024 Construction Notice1_Nassau St.pdf
Nassau St S - McNaughton Av / Montague Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant KGS Group
Document
2024 Construction Notice1_Nassau St.pdf
Norilyn By - Antrim Rd / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Normandy Dr - Lumsden Av / Hollingsworth Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant KGS Group
Document
2024 Construction Notice1_Normandy.pdf
North East Pioneers Greenway Path   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Stantec
Norwood & Main Street Bridge NB & SB Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av/Cumberland Av - Carlton St/Hargrave St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start July 29, 2024
Estimated to end Early September 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Carlton Hargrave Alley.pdf
Notre Dame St - Thibault St / St Jean Baptiste St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Nugent Rd - Hatcher Rd / Rougeau Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 4, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice1_Nugent Road.pdf
Oakenwald Av/Manchester Bv N - Wildwood St/Point Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant KGS Group
Oakview Av/Dunrobin Av - Woodvale St/Kildonan Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant KGS Group
Oakwood Av - Eccles St / Darling St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Osborne 160   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Barnes and Duncan
Document
2024 Construction Notice_160 Osborne St.pdf
Osborne St - Baltimore Rd / Rosedale Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Osborne St - Rosedale Av / St Vital Bridge   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Osborne St to Brandon Av   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start September 3, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_Osborne-Transit AT Pathway.pdf
Oscar Paulsen Park Pathway - Huddersfield Pl / Epsom Cr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start August 23,2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_Oscar Paulson Pathway.pdf
Overton St - Harrowby Av / Blenheim Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 2,2024
Estimated to end Late August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice1_Overton St. Reconstruction.pdf
Panet Rd - Alley North of Clyde Rd / Talbot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 30, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Panet Rd (service road) Rehabilitation-New Pathway.pdf
Panet Rd - Nairn Av / CPR TRacks   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant WSP Canada Inc
Panet Rd - Talbot Av / Nairn Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 30, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice_Panet Rd (service road) Rehabilitation-New Pathway.pdf
Partridge Av (EB) - Aikins St / Salter St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 18, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Partridge.pdf
Partridge Av (EB) - Andrews St / McGregor St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 18, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Partridge.pdf
Partridge Av (EB) - Main St / Aikins St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 18, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Partridge.pdf
Partridge Av (EB) - Powers St / Andrews St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 18, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Partridge.pdf
Partridge Av (EB) - Salter St / Powers St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start June 18, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Partridge.pdf
Peake Av - Robson St / Plessis Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 4, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice1_Peake Avenue.pdf
Pembina Highway Bridge over LaSalle River Rehabilitation (SB)   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Document
2024 Construction Notice_LaSalle Bridge.pdf
Portage Av - Carlton St/Hargrave St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Donald St/Smith St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Garry St/Fort St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Notre Dame Av/Garry St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av - Smith St/Donald St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Ave and Main Street Pedestrian Opening   View Map
Facility type Sidewalk
Type of work New Facility
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Dillon
Additional information Click here
Pritchard Av - Railway St / Chudley St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 10, 2024
Estimated to end Early August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice1_Pritchard Ave Rehabilitation.pdf
Provencher Bv - Langevin St/St Joseph St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Provencher Bv - St Jean Baptiste St/Langevin St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Provencher Bv - St Joseph St/Tache Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Providence Pl - Augusta Dr / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Providence Place.pdf
Queenston By - Mathers Av / Brock St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 13, 2024
Estimated to end Late June 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice2_Queenston Bay Rehabilitation.pdf
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 17, 2024
Estimated to end Early July 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Darco Enterprises
Document
2024 Construction Notice_Redwood Reconstruction1.pdf
Refinery District BRT Pathway Connection   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Refinery District BRT.pdf
Renfrew St - John Brebeuf Pl / Grant Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Renfrew St.pdf
River Av - Harkness St/ Osborne St   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start June 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Preconstruction Notice_Wellington.pdf
River Av - Osborne St/ Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Preconstruction Notice_Wellington.pdf
Riverwood Av/Oakenwald Av - Netley St/Point Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant KGS Group
Roanoke St - Melrose Av E / Pandora Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Robinson St - Flora Av/Dufferin Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start September 9, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_Robinson St Sidewalk Rehabilitation.pdf
Roblin Bv - William R Clement Pw / Roblin Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Rosemount Av - Derek St / Beaumont St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 13, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice2_Rosemount Ave Reconstruction.pdf
Rosemount Av - Wynne St / Derek St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start May 13, 2024
Estimated to end Mid July 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice2_Rosemount Ave Reconstruction.pdf
Rosemount By - Beaumont St / End   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 22, 2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor JC Paving
Document
2024 Construction Notice_Rosemount Bay.pdf
Rudolph By - Snowdon Av / Snowdon Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Rupertsland Av - Main St/Aikins St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 23, 2024
Estimated to end Late June 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice2_Rupertsland Sidewalk - Aikins - Main.pdf
Sadler Av - St Annes Rd / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 29, 2024
Estimated to end Late September 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice_Sadler Ave.pdf
Sage Creek Bv - Warde Av/Lagimodiere Bv (WB)   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Sage Creek Bv -Lagimodiere Bv/Warde Av (EB)   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Sandstone Pl - Scurfield Bv / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Sandstone Place.pdf
Sanford St - Sargent Av / Wellington Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 12, 2024
Estimated to end Late July 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice_Sanford St - Sargent to Wellington.pdf
Saskatchewan Av - Midland St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 6,2024
Estimated to end Late September 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Document
2024 Construction Notice2_Midland and Sask.pdf
Scotland Av - Harrow St / Stafford St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Scotland Ave.pdf
Scotland Av - Harrow St / Wilton St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2024
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Scotland Ave.pdf
Scurfield Bv - #405 / #437   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Scurfield Boulevard - 405 to 437.pdf
Scurfield Bv - #424 / #460   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Scurfield Boulevard - 424 to 460.pdf
Scurfield Bv - #464 / #516   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Scurfield Boulevard - 474 to 516.pdf
Shamrock Dr - Shamrock Dr / Shamrock Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Sinnott St - Barker Bv / Barker Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 6, 2024
Estimated to end Early July, 2024
Approx. % completed Complete
Consultant KGS Group
Contractor Darco Enterprises
Document
2024 Construction Notice2_Sinnott Street.pdf
Smith St/Donald St - Donald St/Ellice Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start July 2, 2024
Estimated to end Early August 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Donald Smith Alley.pdf
Snowdon Av - Treger By / Molson St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Sparling Av - Harrow St / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Preconstruction Notice1_Harrow Sparling.pdf
St Annes Rd - Hindley Av/Worthington Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed Planned
Document
DASZ 15-2020 19-0035 475 St Construction Notice 4.pdf
St Pierre St - Du Couvent Av/De Leglise Av   View Map
Facility type Sidewalk
Type of work New Facility
Estimated to start May 2024
Estimated to end June 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice1_St Pierre St-De L'Eglise St to Du Couvent Ave with FR.pdf
St Vital Bridge   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2025
Approx. % completed 50
Consultant Morrison Hershfield Limited
Sterling Lyon Pw (EB) - Victor Lewis Dr/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Sterling Lyon Pw (EB) - Victor Lewis Dr/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Summerfield Wy - Gilmore Av / Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Summerfield Way.pdf
Taylor Av (EB) - Renfrew St / Lindsay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Taylor Ave.pdf
Taylor Av (WB) - Lindsay St / Kenaston Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27, 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Taylor Ave.pdf
Tranquility Cv - Summerfield Wy / Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Tranquility Cove.pdf
Turnbull Dr - Pembina Hw / City Limit   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Turnbull Drive.pdf
Tyndall Av - Burrows Av/Dorset St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 21, 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2024 Construction Notice2_Dorset St & Tyndall Ave Sidewalk Renewal.pdf
University Cr - 80m North of Dysart Rd/Thatcher Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
University Cr - Markham Rd / 80m North of Dysart Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Wabasha St - Regent Av E / Pandora Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 23, 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Wabasha Street.pdf
Weatherdon Av - Arbuthnot St / Lilac St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27,2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice1_Weatherdon Ave Reconstruction.pdf
Weatherdon Av - Lilac St / Stafford St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27,2024
Estimated to end Mid August 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec
Document
2024 Construction Notice1_Weatherdon Ave Reconstruction.pdf
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 14, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Construction Notice_River Avenue West and Wellington Crescent.pdf
Westbourne Cr - Burland Av / Paddington Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 2024
Estimated to end October 2024
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Westbourne Crescent.pdf
Westgrove Wy - Dale Bv / Dale Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Westgrove.pdf
Wicklow Pl - Dowker Av / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow Pl.pdf
Wicklow St - North Dr / Waterford Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Point to Waterford.pdf
Wicklow St - Oakenwald Av / Dowker Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Waterford to Dowker.pdf
Wicklow St - Point Rd / North Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Point to Waterford.pdf
Wicklow St - Waterford Av / Oakenwald Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Waterford to Dowker.pdf
Wildwood G Pk - South Dr / Wildwood St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 17, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Wildwood H Pk - South Dr / South Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 10, 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Wildwood Park H - South Drive to South Drive.pdf
William Clement Parkway Pathway - Bachelor Ave/Roblin Blvd   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start August 19, 2024
Estimated to end Summer 2025
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_William Clement Pathway.pdf
William Clement Parkway Pathway - Grant Ave/Oakdale Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start August 19, 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_William Clement Pathway.pdf
Woodchester By - Cathcart St/Cathcart St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed Complete
Consultant KGS Group
Contractor J Con Civil
Woodgrove St - Southwood Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant KGS Group
Document
2024 Construction Notice1_Woodgrove St.pdf
Wynford Dr/Ainsdale Wy - Wynford Dr/Wynford Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Fall 2024
Approx. % completed Complete
Consultant Dillon Consulting Limited
Yarwood Av - Lane East of Lipton St / Garfield St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 9, 2024
Estimated to end Early September 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice_Yarwood Av - Garfield N to E End.pdf
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Mid June 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J&D Penner Ltd
Document
2024 Construction Notice1_York Ave.pdf
York Av - Main St / Carlton St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Mid June 2024
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J&D Penner Ltd
Document
2024 Construction Notice1_York Ave.pdf
Young St/Langside St - Sargent Av/Ellice Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start May 23, 2024
Estimated to end Mid June 2024
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2024 Construction Notice2_Langside St Young St Alley.pdf
Youville St - North End / Haig Av   View Map
Facility type Street
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2025
Estimated to end Summer 2025
Approx. % completed Planned
Consultant Dillon Consulting Limited

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.