Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on February 6, 2023 @ 8:00 PM)
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
+
Albina Wy/Raber Rd - Kairistine Ln/Hume St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Alexander Av - Main St / Princess St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
October 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Archibald St - Messier St / Doucet St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Archibald St - Plinguet St / Messier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
+
Beecher Av - Ferrier St / End
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Global Homes
+
Beechtree Cr - Beliveau Rd / Beliveau Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Beliveau Rd E - Marlene St / St Annes Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Biscayne By - McGillivray Pl / McGillivray Pl
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 5, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Bluewater Cr - Cherwell Rd / Cherwell Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Briar Cliff By - Killarney Av / Killarney Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 15, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Additional information
Click here
+
Brotman By - John Forsyth Rd / John Forsyth Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Buller St - Gilbert Av / Manitoba Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 6, 2022
Estimated to end
Early October 2022
Approx. % completed
60
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec Building Services Inc.
Document
+
Byng Pl/Windermere Av - Riverside Dr/Pembina Hw
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
September 6, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
AECOM Canada Ltd
Document
+
Campbell St - Mathers Av / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 20, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Canora St - Preston Av / Westminster Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
80
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Carpathia Rd - 469 Carpathia Rd / Kenaston Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 12, 2022
Estimated to end
Fall 2022
Approx. % completed
70
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Chancellor Dr - Augusta Dr / Quincy By
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 29, 2022
Estimated to end
Spring 2023
Approx. % completed
40
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Countryside Wy - Norris Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 12, 2022
Estimated to end
Early October 2022
Approx. % completed
80
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Cunnington Av - Killarney St / Silverthorne Pl
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Aug 3, 2022
Estimated to end
Late August 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Cunnington Av - St Marys Rd / Killarney St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Aug 3, 2022
Estimated to end
Late August 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Dakota St - Beliveau Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dakota St - Bishop Grandin Bv / Beliveau Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
August 17, 2022
Estimated to end
Late September 2022
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Document
+
De Leglise Av - Campeau St / Pembina Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Dee St - Logan Av / Alexander Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
+
Des Meurons St - Goulet St / Marion St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Downing St - Ellice Av / Armoury Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
30
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Dunkirk Dr - Dunkirk Dr / Kingston Rw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - St Vital Bridge / Norberry Dr
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - St Vital Rd / St Vital Bridge
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Edderton Av - Derek St / Beaumont St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Edmonton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Ellice Av - Carlton St / Kennedy St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
+
Erin St - Notre Dame Ave / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
+
Erin St - Sargent Av / Wolever Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 24,2022
Estimated to end
Fall 2022
Approx. % completed
40
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Eugenie St - Tache Av / St Marys Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
+
Fifth Av/Guay Av - Des Meurons St/St Marys Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Gertrude Av Speed Bump Installation
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 22, 2022
Estimated to end
Mid September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Glenthorne Cr - Greendell Av / Darwin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Glenthorne Cr - Woodlawn Av / Greendell Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Goulet St - Braemar Av / Youville St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grant Av - 150m East of Kenaston / Borebank St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Document
+
Grant Av - Borebank St / Montrose St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 25, 2022
Estimated to end
Fall 2023
Approx. % completed
80
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Document
+
Grant Avenue Pathway - Chalfont Rd/Assiniboine Forest Path
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
September 1, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Greencrest Av - Ulster St / Pembina Hw
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Henderson Hw - City Limit / North of Gilmore Av
View Map
Facility type
Street
Type of work
Study
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
+
Horace St - Des Meurons St / Enfield Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Horace St - Youville St / Des Meurons St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Inkster Bv - McKenzie St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Jewett By - Sinnott St / Sinnott St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 26, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
John Forsyth Rd - Thornewood Av / Warde Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
July 27, 2022
Estimated to end
Mid August 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Johnson Av W - Levis St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Jubilee Av - Cockburn St S / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
+
Jubilee Av - Osborne St / Cockburn St S
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2022
Estimated to end
Fall 2022
Approx. % completed
50
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Keenleyside St - Beach Av / Talbot Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 22, 2022
Estimated to end
Fall 2022
Approx. % completed
60
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Keenleyside St - Talbot Av / Nairn Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 22, 2022
Estimated to end
Fall 2022
Approx. % completed
80
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Keewatin St - Manitoba Av / Selkirk Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
August 23, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Kingston Rw - Dunkirk Dr / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
La Grave St - Lemay Av / Lord Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lagimodiere Bv - Fermor Av / Cottonwood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lakewood Pathway - Lake Park Dr/Clearwater Rd/Edgewater Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
September 20, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Lansdowne Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 27, 2022
Estimated to end
Late September 2022
Approx. % completed
70
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Legion Av - King Edward St / Oddy St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Logan Av - Disraeli Fwy / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Lydia St - McDermot Av / Notre Dame Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
+
Macalester By - Silverstone Av / Silverstone Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Manchester Bv N - Point Rd / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
+
McGregor St - Church Av / Mountain Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McGregor St - Selkirk Av / Dufferin Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McGregor St - Seven Oaks Av / McAdam Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McMeans Av E - Wayoata St / Wabasha St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
October 10, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
McMillan Av/Corydon Av/Donald St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Early September 2022
Estimated to end
Fall 2022
Approx. % completed
50
Document
+
McPhillips St - Machray Av / Mountain Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
+
Midland St - Notre Dame Av / Saskatchewan Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
+
Midwinter Av - Stadacona St / 193 Midwinter Ave
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
September 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Minnetonka St - Avalon Rd / River Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 22, 2022
Estimated to end
Mid September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Moore Av - Dunkirk Dr / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 9, 2022
Estimated to end
Spring 2023
Approx. % completed
0
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - Flynn St / Pulberry St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 9, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - Pulberry St / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 9, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - River Rd / Flynn St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Aug 9, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Mountain Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2023
Approx. % completed
50
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Document
+
Niakwa Trail Pathway - Lagimodiere Bv/Westmount Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
September 19, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Leila Av / Church Av
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
September 14, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec Building Services Inc.
Document
+
Notre Dame Av - Arlington St / McPhillips St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
September 5, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Notre Dame Av - Dublin Av / Wall St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Aug 20, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Notre Dame St - Langevin St / St Joseph St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Oakland Av - Rothesay St / Roch St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
August 15, 2022
Estimated to end
Mid September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Osborne St - Baltimore Rd / Rosedale Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Osborne St - Don Av / Glasgow Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
October 2022
Estimated to end
Fall 2022
Approx. % completed
Planned
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Osborne St - Rosedale Av / St Vital Bridge
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Osborne St - Stradbrook Av / Wardlaw Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Pacific Av - Sherbrook St / Tecumseh St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Fall 2022
Approx. % completed
70
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec Building Services Inc.
Document
+
Palmerston Av - Arlington St / Ethelbert St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
50
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Palmerston Av - Lenore St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Fall 2022
Approx. % completed
80
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Pandora Ave E - Redonda St / Wayoata St
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
July 4, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 9, 2022
Estimated to end
Fall 2022
Approx. % completed
50
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
+
Plessis Rd - St Boniface Rd/City Limit
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 26, 2022
Estimated to end
Early August 2022
Approx. % completed
0
Consultant
AECOM
Document
+
Provencher Bv - Tache Av / Langevin St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
August 29, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Ravine Dr - River Pointe Dr / Settlers Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Redwood Av - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 2022
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
KGS Group Limited
Document
+
Reenders Pathway - Stapon Rd/Panet Rd
View Map
Facility type
Pedestrian / Cycling
Type of work
New Facility
Estimated to start
September 26, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Renfrew St - Grant Av / Taylor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 29, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
RHG Bonney Castle Pathway - Chancellor Dr/Syracuse Cr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
August 18, 2022
Estimated to end
Late September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
River Av - Osborne St / Wellington Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
River Rd - Woodlawn Av / St Marys Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
August 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Roblin Bv - Chalfont Rd / William R Clement Pw
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
August 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Rossmere Cr - Dunvegan St / Kildonan Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
September 23, 2022
Estimated to end
Mid October 2022
Approx. % completed
90
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
Document
+
Salter St - Jefferson Av / Inkster Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
+
Sargent Av - Balmoral St / Edmonton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av - Furby St / Balmoral St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av/Ellice Av - Clifton St/Spruce St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Saskatchewan Av - King Edward St / King Edward St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Saskatchewan Av - King Edward St / Sherwin Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 18, 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Saskatchewan Av - Midland St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
+
Saskatchewan Av - St James St / Century St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Selkirk Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
+
Selkirk Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Summer 2022
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Silver Av - Sturgeon Rd / Hamilton Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
October 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Smith - Graham Av/Midtown Bridge
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Ellice Av / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Notre Dame / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
+
Smith St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
St Annes Rd - Hindley Av/Worthington Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2023
Approx. % completed
0
Document
+
St Annes Rd - St Marys Rd / Fermor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St George Rd - Sadler Av / Hindley Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Stafford St - Corydon Ave/Scotland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 9, 2022
Estimated to end
Fall 2022
Approx. % completed
50
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
Document
+
Stafford St - Scotland Av/Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
+
Stradbrook Av - Queen Elizabeth Wy/Harkness St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Stradbrook Ave - Wellington Cr / Osborne St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Talbot Av - 267 Talbot Av / 168 Talbot Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
September 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Taylor Ave - Harrow St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
Document
+
Tecumseh St - Alexander Av / Pacific Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2022
Estimated to end
Fall 2022
Approx. % completed
70
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec Building Services Inc.
+
Telfer St N - St Matthews Av / Ellice Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 14, 2022
Estimated to end
Fall 2022
Approx. % completed
60
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Tu Pelo Av - London St / West of Jeffrey Cr
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Aug 8, 2022
Estimated to end
Early September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Tu Pelo Av - London St / West of Jeffrey Cr
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Aug 8, 2022
Estimated to end
Early September 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Tulane By - Pasadena Av / Pasadena Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
University Cr - Pembina Hw / Thatcher Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 18, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Document
+
University Cr - Thatcher Dr / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Spring 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Document
+
Victoria Av E - Roanoke St / Leola St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 1, 2022
Estimated to end
Fall 2022
Approx. % completed
80
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Document
+
Wall St - Wellington Av / Notre Dame Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 16,2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
Document
+
Waller Av/Clarence Av - Hudson St/Marshall Cr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Spring 2023
Approx. % completed
5
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Wellington Cr - River Av / Stradbrook Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Weston St - Alexander Av / Pacific Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
August 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Whellams Ln - Claus By / Appleton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
August 5, 2022
Estimated to end
Late August 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
William Av - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Fall 2022
Approx. % completed
60
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
September 19, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
September 19, 2022
Estimated to end
Fall 2022
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Yukon Av - Milt Stegall Dr / St James St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Late June 2022
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.