Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on November 26, 2026 @ 10:30 AM)
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Contractor
GIP Prairie Ltd.
+
Abinojii Mikanah WB to Pembina Hw NB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Austin St - Higgins Av / Henry Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 15, 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Baylor Av and Newcastle Rd Cut-Thru
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Document
+
Bertrand St - Des Meurons St/Youville St
View Map
Facility type
Street
Type of work
Asphalt Overlay
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Contractor
GIP Prairie Ltd.
Document
+
Brunswick St - Burnett Av/McLeod Av
View Map
Facility type
Street
Type of work
Asphalt Overlay
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
+
Carlaw Av - Nassau St S / Daly St S
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
July 20, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Document
+
Carlton St - Cumberland Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Carlton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Carlton St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Carlton St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Carlton St - York Av / Broadway
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Chancellor Dr - Markham Rd / Path
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 8, 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Document
+
Concordia Ave Multi-Use Pathway
View Map
Facility type
Pedestrian / Cycling
Type of work
New Construction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
50
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Corydon Av (EB) - Edgeland Bv / Kenaston Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Corydon Av (EB) - Tuxedo Av / Edgeland Bv
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Corydon Av (WB) - Handsart Bv / Shaftesbury Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Corydon Av (WB) - Tuxedo Av / Handsart Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Dells Cr - Wales Av / Hazelwood Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Document
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 22, 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Contractor
GIP Prairie Ltd.
Document
+
Edmonton St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
April 20, 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
Edmonton St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
April 20, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Document
+
English Pl - Darwin St / Darwin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Document
+
Evans St/Archibald - Prosper St/St Catherine St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
September 2,2026
Estimated to end
Fall 2026
Approx. % completed
0
Document
+
Greenlea Cv - Gilmore Av / Gilmore Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
July 27, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
JC Paving
Document
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
30
Consultant
Dillon Consulting Limited
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
30
Consultant
Dillon Consulting Limited
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
30
Consultant
Dillon Consulting Limited
+
Hargrave St - Cumberland Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Hargrave St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Hargrave St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
Henderson Hw - Glenway Av/Fortier Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Henry Av - Gunnell St / Sherbrook St
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
June 29, 2026
Estimated to end
Fall 2026
Approx. % completed
60
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Highfield St/Coniston St - Monck Av/Claremont Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
July 16, 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Dillon Consulting Limited
Document
+
Inman Av/Fermor Av - St Thomas Rd/St Marys Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Jarvis Av - Andrews St / McGregor St
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
September 8, 2026
Estimated to end
Fall 2026
Approx. % completed
40
Consultant
City Of Winnipeg - Engineering Division
Document
+
Jarvis Av - McKenzie St / Parr St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
September 8, 2026
Estimated to end
Fall 2026
Approx. % completed
40
Consultant
City Of Winnipeg - Engineering Division
Document
+
Jarvis Av - McPhillips St/Parr St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 6, 2026
Estimated to end
Fall 2026
Approx. % completed
40
Consultant
City Of Winnipeg - Engineering Division
Document
+
Jarvis Av - Powers St / Andrews St
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
September 8, 2026
Estimated to end
Fall 2026
Approx. % completed
40
Consultant
City Of Winnipeg - Engineering Division
Document
+
Kennedy St - Ellice Av / Qu'Appelle Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 25, 2026
Estimated to end
Fall 2026
Approx. % completed
50
Consultant
WSP Canada Inc
Document
+
Kennedy St - Qu'Appelle Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 25, 2026
Estimated to end
Fall 2026
Approx. % completed
30
Consultant
WSP Canada Inc
Document
+
Kings Dr - Silverstone Av / Kilkenny Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 8, 2026
Estimated to end
Fall 2026
Approx. % completed
50
Consultant
Stantec Consulting Ltd
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 8, 2026
Estimated to end
Fall 2026
Approx. % completed
50
Consultant
Stantec Consulting Ltd
Document
+
La Porte Pl/Le Maire St - La Porte Pl/Le Maire St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Document
+
Lagimodiere Bv - Almey Av / CNR Overpass
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv - CNR Overpass / Grassie Bv
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv - Concordia Av E / Lagimodiere Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv - Grassie Bv / CNR Overpass
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv - Lagimodiere Bv / Lagimodiere Bv
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Lagimodiere Bv Overpass over CPR Keewatin
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
40
Additional information
Click here
+
Litz Pl - Henderson Hw / Appleton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 17, 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Contractor
JC Paving
Document
+
Magdalene By and Loyola By Cut-Thru
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Document
+
Marion St/Horace St - East Limit/Youville St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Marshall Cr - Waller Av / Clarence Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
McDermot Av / Notre Dame Av - Notre Dame Av / Tecumseh St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
August 17, 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
McKenzie St - Hartford Av / Jefferson Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 19, 2026
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
City Of Winnipeg - Engineering Division
Document
+
McKenzie St - Kingsbury Av / Hartford Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 6, 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
City Of Winnipeg - Engineering Division
Document
+
McMillan Av / Corydon Av - Hugo St N / Cockburn St N
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
August 24, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Document
+
Mount Allison By and Lafayette By Cut-Thru
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Stantec Consulting Ltd
Document
+
Nassau St S - Brandon Av / Hethrington Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 20, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Document
+
Nassau St S - Hethrington Av / Morley Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 20, 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Document
+
Osborne St/Nassau St S - Kylemore Av/Walker Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Osborne St/Nassau St S - Walker Av/Rathgar Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Panet Rd - Nairn Av / CPR TRacks
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 24, 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Paufeld Dr - Karen St / Rothesay St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
60
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Pembina Hw NB to Abinojii Mikanah EB
View Map
Facility type
Bridge
Type of work
Minor Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Document
+
Pembina Hw NB to Abinojii Mikanah WB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Document
+
Perth Av - McGregor St / Parr St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
+
Plessis Rd - 560 Plessis Rd / St Boniface Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
+
Plessis Rd - 996 Plessis Rd / St Boniface Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
+
Plessis Rd - St Boniface Rd / 560 Plessis Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
+
Plumtree Pl - Meadowood Dr / Meadowood Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Document
+
Portage Av - Banting Dr / Sturgeon Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
May 11, 2026
Estimated to end
Summer 2026
Approx. % completed
Complete
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
July 20, 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Riverwood Av/Oakenwald Av - Point Rd/Lyon St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Rosseau Av W / Ravelston Av W - Brewster St / Plessis Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
September 2,2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
Dillon Consulting Limited
Document
+
Sage North Development Phase 1A Contract 5A
View Map
Facility type
Street
Type of work
New - Street Construction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Sage North Development Phase 1A Contract 5C
View Map
Facility type
Street
Type of work
New - Street Construction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Sandralin By - End / Avalon Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
September 1, 2026
Estimated to end
Fall 2026
Approx. % completed
60
Consultant
Stantec Consulting Ltd
Document
+
Sherbrook St - Broadway/ Comberland Ave
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
May 19, 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
AECOM Canada Ltd
Document
+
Silverstone Av Sidewalk (South Side)
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Document
+
St Anthony Av - McGregor St / Parr St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 23, 2026
Estimated to end
Fall 2026
Approx. % completed
60
Consultant
City Of Winnipeg - Engineering Division
Document
+
St Mary Av - Edmonton St / Memorial Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
April 27, 2026
Estimated to end
Fall 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
St Marys Rd - Abinojii Mikanah / Dakota St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 11, 2026
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Document
+
St Marys Rd - Fermor Av / Arden Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 11, 2026
Estimated to end
Fall 2026
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Document
+
St Marys Rd - PTH 100 / Chrypko Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
St Marys Rd - St Vital Rd / Fermor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 11, 2026
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Document
+
Sutherland Av - Charles St/Aikins St
View Map
Facility type
Sidewalk
Type of work
New Facility - Sidewalk
Estimated to start
August 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Tache Av - Messager St/Darveau St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 13,2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
University Cr - 80m North of Dysart Rd/Thatcher Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Summer 2026
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
University Cr - Markham Rd / 80m North of Dysart Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Summer 2026
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Victory Pl/Sherwood Pl - St Annes Rd/St Marys Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
+
Weatherdon Av - Stafford St / Harrow St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 10, 2026
Estimated to end
Fall 2026
Approx. % completed
50
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Document
+
York Av - Carlton St / Kennedy St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
York Av - Kennedy St / Vaughan St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
+
York Av - Vaughan St / Memorial Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2026
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
WSP Canada Inc
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.