Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links

Holiday seasonView holiday hours for City of Winnipeg facilities and services from December 24 to January 1.

Holiday seasonView holiday hours for City of Winnipeg facilities and services from December 24 to January 1.

Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on December 26, 2024 @ 1:00 PM)
 
 


Assiniboine Park Pedestrian Bridge   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cadiz By - Malone St / Buckle St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Cadiz.pdf
Cumberland Av/Carlton St - Cumberland Av/Qu'Appelle Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Cumberland Av/Hargrave St - Cumberland Av/Ellice Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Document
2024 Construction Notice_Hargrave Donald Alley.pdf
Dearborn Av - Lacy St / Brazier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 70
Consultant Dillon Consulting Limited
Eldridge Av - Elmhurst Rd / Haney St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Eldridge Ave.pdf
Ellice Av - Strathcona St / Empress St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 26, 2024
Estimated to end Summer 2025
Approx. % completed 90
Consultant WSP Canada Inc
Document
2024 Construction Notice_Ellice_Revised.pdf
Fortier Av - Summerfield Wy / Pentland St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Fortier Ave.pdf
Freemont By - Fairlane Av / Fairlane Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Freemont.pdf
Gerrond By - Cavalier Dr / Cavalier Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant KGS Group
Document
2024 Construction Notice1_Gerrond.pdf
Ghent Cv - Mayfield Cr / Mayfield Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Ghent Cove.pdf
Gordon Av - Stadacona St / Brazier St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant Dillon Consulting Limited
Green Valley By - Louelda St / Louelda St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Hood Av - Scarfe St / Leahcrest Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 14, 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Hood Avenue.pdf
Irene St - Sony Pl / Waller Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 27, 2024
Estimated to end Summer 2025
Approx. % completed 20
Consultant WSP Canada Inc
Contractor Darco Enterprises
Document
2024 Construction Notice1_Irene Street.pdf
Kullman St - Snowdon Av / Kimberly Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
McGregor St - Alley South of Partridge Av / Kingsbury Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Document
2024 Construction Notice_McGregor.pdf
Melrose Av E - Leola St / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant Dillon Consulting Limited
Montgomery Av - Fisher St / Casey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant KGS Group
Document
2024 Construction Notice1_Montgomery Av.pdf
Nassau St S - Jubilee Av / McNaughton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant KGS Group
Document
2024 Construction Notice1_Nassau St.pdf
Nassau St S - McNaughton Av / Montague Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant KGS Group
Document
2024 Construction Notice1_Nassau St.pdf
Norilyn By - Antrim Rd / Antrim Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Norwood & Main Street Bridge NB & SB Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Osborne St - Baltimore Rd / Rosedale Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Osborne St - Rosedale Av / St Vital Bridge   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Pembina Highway Bridge over LaSalle River Rehabilitation (SB)   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Document
2024 Construction Notice_LaSalle Bridge.pdf
Portage Ave and Main Street Pedestrian Opening   View Map
Facility type Sidewalk
Type of work New Facility
Estimated to start Winter 2024 - 2025
Estimated to end Summer 2025
Approx. % completed 0
Consultant Dillon
Additional information Click here
Document
Portage and Main Pedestrian Opening Construction Notice - Dec 16 2024.pdf
Roanoke St - Melrose Av E / Pandora Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 5
Consultant Dillon Consulting Limited
Rudolph By - Snowdon Av / Snowdon Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Snowdon Av - Treger By / Molson St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
St Vital Bridge   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2025
Approx. % completed 50
Consultant Morrison Hershfield Limited
Summerfield Wy - Gilmore Av / Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Summerfield Way.pdf
Taylor Av (EB) - Renfrew St / Lindsay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Taylor Ave.pdf
Taylor Av (WB) - Lindsay St / Kenaston Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 27, 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor JC Paving
Document
2024 Construction Notice2_Taylor Ave.pdf
Tranquility Cv - Summerfield Wy / Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 9,2024
Estimated to end Summer 2025
Approx. % completed 60
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Tranquility Cove.pdf
Turnbull Dr - Pembina Hw / City Limit   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Document
2024 Preconstruction Notice1_Turnbull Drive.pdf
University Cr - 80m North of Dysart Rd/Thatcher Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
University Cr - Markham Rd / 80m North of Dysart Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2025
Approx. % completed 40
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Wabasha St - Regent Av E / Pandora Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 23, 2024
Estimated to end Summer 2025
Approx. % completed 80
Consultant Dillon Consulting Limited
Document
2024 Construction Notice_Wabasha Street.pdf
Westgrove Wy - Dale Bv / Dale Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Westgrove.pdf
Wicklow Pl - Dowker Av / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow Pl.pdf
Wicklow St - North Dr / Waterford Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Point to Waterford.pdf
Wicklow St - Oakenwald Av / Dowker Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Waterford to Dowker.pdf
Wicklow St - Point Rd / North Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Point to Waterford.pdf
Wicklow St - Waterford Av / Oakenwald Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Wicklow St - Waterford to Dowker.pdf
William Clement Parkway Pathway - Grant Ave/Oakdale Dr   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start August 19, 2024
Estimated to end Summer 2025
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Document
2024 Construction Notice_William Clement Pathway.pdf
Woodgrove St - Southwood Av / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant KGS Group
Document
2024 Construction Notice1_Woodgrove St.pdf

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.