Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on November 22, 2024 @ 8:00 PM)
+
Abinojii Mikanah (EB) - Dakota St / St Annes Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Abinojii Mikanah (EB) - River Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Abinojii Mikanah (EB) - St Marys Rd / Dakota St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 20, 2024
Estimated to end
Late September 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Archibald St - Messier St / Doucet St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Additional information
Click here
Document
+
Archibald St - Plinguet St / Messier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Additional information
Click here
Document
+
Arlington Bridge Reconstruction - Selkirk Av / McDermot Av
View Map
Facility type
Bridge
Type of work
Study
Estimated to start
Study
Estimated to end
Study
Approx. % completed
Study
Additional information
Click here
+
Assiniboine Av - Navy Wy / Hargrave St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Wintec
Document
+
Augusta Dr - Chancellor Dr / Greensboro Sq
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Augusta Dr - Chancellor Dr / Lakeside Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Augusta Dr - Lakeside Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Bayshore Cv - Beaverhill Bv / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Baywater Pl - Beaverhill Bv / Beaverhill Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Beaumont St - Waterford By (S leg) / McGillivray Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
+
Beecher Av - Ferrier St / End
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Global Homes
+
Bison Dr - 75m West of Pembina Hw / Markham Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Blenheim Av - Des Meurons St / St Annes Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27,2024
Estimated to end
September 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Brady Rd - Ethan Boyer Way / Brady Road Landfill Access
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Bridge Lake Dr - Traffic Calming
View Map
Facility type
Pedestrian / Cycling
Type of work
New Facility
Estimated to start
September 9,2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Document
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
April 29, 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Additional information
Click here
Document
+
Broadway - Spence St / Sherbrook St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
August 8, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
J&D Penner Ltd
Document
+
Brock St - Mathers Av / Taylor Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 24, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Cadiz By - Malone St / Buckle St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Camiel Sys St - Plessis Rd / Mazenod Rd
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Carlyle By - Westwood Dr / Westwood Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 6, 2024
Estimated to end
Early July, 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Darco Enterprises
Document
+
Carruthers Av - Cottingham St / 1037 Lansdowne Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
+
Carruthers Av - Sinclair St / Airlies St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 23, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Document
+
Caton St - Des Meurons St / St Marys Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Champlain St - Niverville Av / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Charles St - Machray Av / Church Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 3, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Church Av - Main St / Charles St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2024
Estimated to end
August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Clare Av - Eccles St / Fisher St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
+
Clare Av - Fisher St / Casey St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
+
Cochrane St - Inkster Bv / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 10, 2024
Estimated to end
Late July, 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Cochrane St - Lansdowne Av / Inkster Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 10, 2024
Estimated to end
Late July, 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Collegiate St - St Matthews Av / Silver Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 6, 2024
Estimated to end
Early July, 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Darco Enterprises
Document
+
Courtwood Pl - Beaverhill Bv / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Creek Bend Road Bridge Replacement
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Additional information
Click here
+
Cumberland Av/Carlton St - Cumberland Av/Qu'Appelle Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
+
Cumberland Av/Hargrave St - Cumberland Av/Ellice Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Document
+
Cumberland Av/Sargent Av - Furby St/Sherbrook St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Wintec
Document
+
Dahlia Av - End / Sinclair St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 14, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Document
+
Dakota St - Beliveau Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 8,2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Wintec
Document
+
Dakota St - Bishop Grandin Bv / Beliveau Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 8,2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Wintec
Document
+
Daly St N - Pembina Hw / Lorette Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Day St - Pandora St / Regent Av
View Map
Facility type
Pedestrian / Cycling
Type of work
Rehabilitation
Estimated to start
September 23, 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Additional information
Click here
Document
+
De La Cathedrale Av/Hamel Av - Des Meurons St/De La Morenie St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Wintec
Document
+
Dearborn Av - Lacy St / Brazier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
70
Consultant
Dillon Consulting Limited
+
Delorme By - Grandmont Bv / Grandmont Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Dorge Dr - Gendreau Av / Le Maire St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Dorset St - Burrows Av/Tyndall Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 21, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Du Couvent Av - Entrance Approach/St Pierre St
View Map
Facility type
Sidewalk
Type of work
New Facility
Estimated to start
May 2024
Estimated to end
June 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Dudley Av - Daly St N / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Dufferin Av - King St/Robinson St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
September 9, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Dufferin Av - Robinson St/Aikins St
View Map
Facility type
Sidewalk
Type of work
Rehabilitation
Estimated to start
September 9, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Dugald Rd (EB) - Ravenhurst St / 390m east of Ravenhurst St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 9,2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Document
+
Dumoulin St - Thibault St / Langevin St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Dunkirk Dr - Dunkirk Dr / Kingston Rw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - St Vital Bridge / Norberry Dr
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - Kingston Rw / Dunkirk Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Dr - St Vital Rd / St Vital Bridge
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dunkirk Pl - Kingston Rw / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
July 24, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Dunraven Av - Overton St / St Marys Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 3, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Edderton Av - Derek St / Beaumont St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 13, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Edderton By - Beaumont St / End
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
August 12, 2024
Estimated to end
Mid September 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Egerton Rd - Morier Av / South End
View Map
Facility type
Street
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Eldridge Av - Elmhurst Rd / Haney St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Ellice Av - Ashburn St / Strathcona St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 26, 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Document
+
Ellice Av - Erin St / Ashburn St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 26, 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Document
+
Ellice Av - Strathcona St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 26, 2024
Estimated to end
Summer 2025
Approx. % completed
90
Consultant
WSP Canada Inc
Document
+
Fairlane Av - Isbister St / Buchanan Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 6, 2024
Estimated to end
Early July, 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Darco Enterprises
Document
+
Fisher St - Arnold Av / Morley Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 7, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Fisher St - Montgomery Av / Churchill Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 7, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Fisher St - Morley Av / Oakwood Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 7, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Fortier Av - Summerfield Wy / Pentland St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Fowler St/Main St - Anderson Av/St Johns Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 2024
Estimated to end
August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Freemont By - Fairlane Av / Fairlane Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Furby St - McDermot Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 22, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Furby St - William Av / Bannatyne Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 22, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Gerrond By - Cavalier Dr / Cavalier Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
KGS Group
Document
+
Ghent Cv - Mayfield Cr / Mayfield Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Gibraltar By - Normandy Dr / Normandy Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
KGS Group
Document
+
Golspie St - Munroe Av / Watt St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 26, 2024
Estimated to end
Early August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Gordon Av - Stadacona St / Brazier St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
Dillon Consulting Limited
+
Goulet St - Traverse Av / Youville St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Bituminex Paving Ltd
Additional information
Click here
Document
+
Grant Av (EB) - Rockwood St / Wilton St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Grant Av (EB) - Wilton St / Stafford St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Grant Av (WB) - Stafford St / Harrow St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Green Valley By - Louelda St / Louelda St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Greensboro By - Chancellor Dr / Augusta Dr
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Greensboro Sq - Greensboro By / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Gunnell St - Logan Av / Alexander Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
June 17, 2024
Estimated to end
Early July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Haggart Av - Meridian Dr / 195 Haggart Av
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Harrow St - Harrow St E / Sparling Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Harrow St - Taylor Av / Pembina Hw
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
+
Hartford Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Hartford Av - McGregor St / Salter St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 19, 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Hood Av - Scarfe St / Leahcrest Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 14, 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
Document
+
Howard Kendel Pl - McLellan Dr / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 2, 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Document
+
Inkster Bv (EB) - Andrews St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - Fife St / Lansdowne Av
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - Lansdowne Av / McPhillips St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - McGregor St / Andrews St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2025
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - McKenzie St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2025
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - McKenzie St / McGregor St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - Sheppard St / Milner St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Inkster Bv (EB) - Sinclair St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Nelson River Construction
Document
+
Irene St - Sony Pl / Waller Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Summer 2025
Approx. % completed
20
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Irene St - Waller Av / Clarence Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27, 2024
Estimated to end
Mid September 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Jubilee Av - Cockburn St S / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Kanata St - Ravelston Av E / Regent Av E
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Kanata St - Regent Av E / Pandora Av E
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Keewatin St - Burrows Av/Gallagher Av W
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
90
+
Kern Dr - Roanoke St / Kanata St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Kingston Rw - Dunkirk Dr / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Kullman St - Snowdon Av / Kimberly Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Lagimodiere Bv - 145m North of Sage Creek Bv / Bishop Grandin Bv
View Map
Facility type
Street
Type of work
Mill & Fill
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Lagimodiere Bv - Bishop Grandin Bv / Fermor Av
View Map
Facility type
Street
Type of work
Mill & Fill
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Lagimodiere Bv - Fermor Av / Cottonwood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Wintec
Document
+
Lagimodiere Bv - Warman Rd/Dugald Rd
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Langside St - Cumberland Av / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Wintec
Document
+
Lansdowne Av - St Cross St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 10, 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Lenore St/Ruby St - Preston Av/Westminster Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
June 26, 2024
Estimated to end
Mid September 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lilian Av - Poulin Pl / Cromwell St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Linwood St - Bruce Av/Portage Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Linwood St - Ness Av/Bruce Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lipton St - Portage Av / Westminster Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Document
+
Lipton St - Westminster Av / Wolseley Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Document
+
Lipton St - Wolseley Av / Palmerston Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Document
+
Lismore Av - Oddy St / King Edward St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 3, 2024
Estimated to end
Early July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Logan Av - Blake St/Vine St (Rail Crossing)
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Lorette Av - Daly St N / Pembina Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 21,2024
Estimated to end
Early August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Luxton Av - Scotia St / St Cross St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2024
Estimated to end
August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Machray Av - Main St / Aikins St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Manahan Av - Pembina Hw / Hudson St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 31, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
+
Mazenod Rd - De Baets St / Camiel Sys St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
McAdam Av (EB) - End / Scotia St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 21,2024
Estimated to end
Early August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
McAdam Av (WB) - Scotia St / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2024
Estimated to end
August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
McAdam Av - Lane / Sinclair St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
McGregor St (NB) - Partridge Av / Leila Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St (SB) - Leila Av / Partridge Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St - Alley South of Partridge Av / Kingsbury Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St - Burrin Av / Jefferson Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St - Jefferson Av / Seven Oaks Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St - Kingsbury Av / Burrin Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McGregor St - Partridge Av/ Alley South of Partridge Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 13, 2024
Estimated to end
Late October 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
McMahon Pl - McLellan Dr / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 2, 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Document
+
McMicken St - Cumberland Av / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
Contractor
Wintec
Document
+
Melrose Av E - Leola St / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
Dillon Consulting Limited
+
Meridian Dr - Discovery Pl / Inksbrook Dr
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Midland St - Notre Dame Av / Saskatchewan Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 6,2024
Estimated to end
Late September 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Moberly Av - Sanford Fleming Rd / Cambie Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 21, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bituminex Paving Ltd
Document
+
Montclair By - Lakeshore Rd / Lakeshore Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Montgomery Av - Fisher St / Casey St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
KGS Group
Document
+
Montrose St - Grant Av / Mathers Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
+
Moray Street Bridge Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Mount Auburn By - Garton Av / Garton Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 24, 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Nassau St S - Jubilee Av / McNaughton Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
KGS Group
Document
+
Nassau St S - McNaughton Av / Montague Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
KGS Group
Document
+
Norilyn By - Antrim Rd / Antrim Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Normandy Dr - Lumsden Av / Hollingsworth Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
KGS Group
Document
+
North East Pioneers Greenway Path
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Stantec
+
Norwood & Main Street Bridge NB & SB Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Notre Dame Av/Cumberland Av - Carlton St/Hargrave St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
July 29, 2024
Estimated to end
Early September 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Document
+
Notre Dame St - Thibault St / St Jean Baptiste St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Nugent Rd - Hatcher Rd / Rougeau Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 4, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bituminex Paving Ltd
Document
+
Oakenwald Av/Manchester Bv N - Wildwood St/Point Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
KGS Group
+
Oakview Av/Dunrobin Av - Woodvale St/Kildonan Dr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
KGS Group
+
Oakwood Av - Eccles St / Darling St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Barnes and Duncan
Document
+
Osborne St - Baltimore Rd / Rosedale Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Osborne St - Rosedale Av / St Vital Bridge
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Facility type
Pedestrian / Cycling
Type of work
New Facility
Estimated to start
September 3, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Document
+
Oscar Paulsen Park Pathway - Huddersfield Pl / Epsom Cr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
August 23,2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Document
+
Overton St - Harrowby Av / Blenheim Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 2,2024
Estimated to end
Late August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Panet Rd - Alley North of Clyde Rd / Talbot Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 30, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Panet Rd - Nairn Av / CPR TRacks
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Panet Rd - Talbot Av / Nairn Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 30, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Partridge Av (EB) - Aikins St / Salter St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 18, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Partridge Av (EB) - Andrews St / McGregor St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 18, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Partridge Av (EB) - Main St / Aikins St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 18, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Partridge Av (EB) - Powers St / Andrews St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 18, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Partridge Av (EB) - Salter St / Powers St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
June 18, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Peake Av - Robson St / Plessis Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 4, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Bituminex Paving Ltd
Document
+
Pembina Highway Bridge over LaSalle River Rehabilitation (SB)
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Document
+
Portage Av - Carlton St/Hargrave St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - Donald St/Smith St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - Garry St/Fort St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - Notre Dame Av/Garry St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av - Smith St/Donald St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Ave and Main Street Pedestrian Opening
View Map
Facility type
Sidewalk
Type of work
New Facility
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Dillon
Additional information
Click here
+
Pritchard Av - Railway St / Chudley St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 10, 2024
Estimated to end
Early August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Provencher Bv - Langevin St/St Joseph St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Provencher Bv - St Jean Baptiste St/Langevin St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Provencher Bv - St Joseph St/Tache Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Providence Pl - Augusta Dr / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Queenston By - Mathers Av / Brock St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 13, 2024
Estimated to end
Late June 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Redwood Av - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 17, 2024
Estimated to end
Early July 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Darco Enterprises
Document
+
Refinery District BRT Pathway Connection
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
Renfrew St - John Brebeuf Pl / Grant Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
+
River Av - Harkness St/ Osborne St
View Map
Facility type
Pedestrian / Cycling
Type of work
New Facility
Estimated to start
June 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
River Av - Osborne St/ Wellington Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Riverwood Av/Oakenwald Av - Netley St/Point Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
KGS Group
+
Roanoke St - Melrose Av E / Pandora Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Robinson St - Flora Av/Dufferin Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
September 9, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bayview Construction Ltd
Document
+
Roblin Bv - William R Clement Pw / Roblin Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Rosemount Av - Derek St / Beaumont St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 13, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Rosemount Av - Wynne St / Derek St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
May 13, 2024
Estimated to end
Mid July 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Rosemount By - Beaumont St / End
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 22, 2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
JC Paving
Document
+
Rudolph By - Snowdon Av / Snowdon Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
+
Rupertsland Av - Main St/Aikins St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 23, 2024
Estimated to end
Late June 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Sadler Av - St Annes Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 29, 2024
Estimated to end
Late September 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Sage Creek Bv - Warde Av/Lagimodiere Bv (WB)
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Sage Creek Bv -Lagimodiere Bv/Warde Av (EB)
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Sandstone Pl - Scurfield Bv / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Sanford St - Sargent Av / Wellington Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 12, 2024
Estimated to end
Late July 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Saskatchewan Av - Midland St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 6,2024
Estimated to end
Late September 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Scotland Av - Harrow St / Stafford St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
+
Scotland Av - Harrow St / Wilton St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Bituminex Paving Ltd
Document
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Shamrock Dr - Shamrock Dr / Shamrock Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Sinnott St - Barker Bv / Barker Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 6, 2024
Estimated to end
Early July, 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
Darco Enterprises
Document
+
Smith St/Donald St - Donald St/Ellice Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
July 2, 2024
Estimated to end
Early August 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Document
+
Snowdon Av - Treger By / Molson St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
+
Sparling Av - Harrow St / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
St Annes Rd - Hindley Av/Worthington Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
Planned
Document
+
St Pierre St - Du Couvent Av/De Leglise Av
View Map
Facility type
Sidewalk
Type of work
New Facility
Estimated to start
May 2024
Estimated to end
June 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
Morrison Hershfield Limited
+
Sterling Lyon Pw (EB) - Victor Lewis Dr/Kenaston Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Sterling Lyon Pw (EB) - Victor Lewis Dr/Kenaston Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
+
Summerfield Wy - Gilmore Av / Gilmore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Taylor Av (EB) - Renfrew St / Lindsay St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Taylor Av (WB) - Lindsay St / Kenaston Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27, 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Tranquility Cv - Summerfield Wy / Gilmore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Turnbull Dr - Pembina Hw / City Limit
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Tyndall Av - Burrows Av/Dorset St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 21, 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Bituminex Paving Ltd
Document
+
University Cr - 80m North of Dysart Rd/Thatcher Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
University Cr - Markham Rd / 80m North of Dysart Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Wabasha St - Regent Av E / Pandora Av E
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 23, 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
Dillon Consulting Limited
Document
+
Weatherdon Av - Arbuthnot St / Lilac St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27,2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Weatherdon Av - Lilac St / Stafford St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27,2024
Estimated to end
Mid August 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec
Document
+
Wellington Cr - River Av / Stradbrook Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 14, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Westbourne Cr - Burland Av / Paddington Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 2024
Estimated to end
October 2024
Approx. % completed
Complete
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
Westgrove Wy - Dale Bv / Dale Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wicklow St - North Dr / Waterford Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wicklow St - Oakenwald Av / Dowker Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wicklow St - Point Rd / North Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wicklow St - Waterford Av / Oakenwald Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wildwood G Pk - South Dr / Wildwood St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 17, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
+
Wildwood H Pk - South Dr / South Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 10, 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
William Clement Parkway Pathway - Bachelor Ave/Roblin Blvd
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
August 19, 2024
Estimated to end
Summer 2025
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Document
+
William Clement Parkway Pathway - Grant Ave/Oakdale Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
August 19, 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
City Of Winnipeg - Engineering Division
Document
+
Woodchester By - Cathcart St/Cathcart St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Summer 2024
Approx. % completed
Complete
Consultant
KGS Group
Contractor
J Con Civil
+
Woodgrove St - Southwood Av / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Wynford Dr/Ainsdale Wy - Wynford Dr/Wynford Dr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Fall 2024
Approx. % completed
Complete
Consultant
Dillon Consulting Limited
+
Yarwood Av - Lane East of Lipton St / Garfield St N
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 9, 2024
Estimated to end
Early September 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Mid June 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
J&D Penner Ltd
Document
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Mid June 2024
Approx. % completed
Complete
Consultant
City Of Winnipeg - Engineering Division
Contractor
J&D Penner Ltd
Document
+
Young St/Langside St - Sargent Av/Ellice Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 23, 2024
Estimated to end
Mid June 2024
Approx. % completed
Complete
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Youville St - North End / Haig Av
View Map
Facility type
Street
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2025
Estimated to end
Summer 2025
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.