Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on June 6, 2023 @ 8:00 PM)
+
Academy Rd - Renfrew St / Wellington Cr S
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Agate By - Drake Bv / Drake Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Ainsworth Pl - Kirkbridge Dr / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Albina Wy/Raber Rd - Kairistine Ln/Hume St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 17, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Alexander Av - Lily St / Martha St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Alwood Cr - Egesz St / Egesz St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 15, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Ansell Ct - Fernbank Av / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Archibald St - Messier St / Doucet St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
October 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
Document
+
Archibald St - Plinguet St / Messier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
October 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
To Be Determined
Additional information
Click here
Document
+
Argyle St - Waterfront Dr / George Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Arthur St - Notre Dame Av / McDermot Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Ash St - Wellington Cr / Academy Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Assiniboine Av - Navy Wy / Hargrave St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 15, 2023
Estimated to end
July 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Atlantic Av- Main St/Salter St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Audubon Pl - Lake Grove By / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Bairdmore Bv - Service Road 832/910
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Balmoral St - Ellice Av / 458 Balmoral St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Baltimore Rd - Casey St / Hay St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Baltimore Rd - Fisher St / Casey St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Beaulynn Cv - Allendale Dr / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beaumont St - Waterford By (S leg) / McGillivray Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Beecher Av - Ferrier St / End
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Global Homes
+
Beechtree Cr - Beliveau Rd / Beliveau Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 22, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Beghin Av - De Baets St / Paquin Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Beliveau Rd E - Marlene St / St Annes Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 8,2023
Estimated to end
Early June 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Benbow Rd - Egesz St / Burrows Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Bentall St - Mountain Av / Redwood Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 29, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Birchdale Av/Lawndale Av - Conniston St/Lyndale Dr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 9, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
+
Biscayne By - McGillivray Pl / McGillivray Pl
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 5, 2022
Estimated to end
Spring 2023
Approx. % completed
90
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Bison Dr - 75m West of Pembina Hw / Markham Rd
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Bluewater Cr - Cherwell Rd / Cherwell Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 22, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Briar Cliff By - Killarney Av / Killarney Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 8, 2022
Estimated to end
Late May 2023
Approx. % completed
80
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Additional information
Click here
+
Broadway - Osborne St / Main St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Additional information
Click here
Document
+
Broadway - Spence St / Sherbrook St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
October 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Broadway/Sara Av - Sherbrook St/Maryland St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Bronx Av - Brazier St / Henderson Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Bronx Av - Roch St / Brazier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Brookhaven By - Lakewood Bv/Lakewood Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Brotman By - John Forsyth Rd / John Forsyth Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 22, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Bunting St - Inkster Bv / Church Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 15, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Burrows Av - Aikins St / Charles St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 5, 2023
Estimated to end
Early July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Byng Pl/Windermere Av - Riverside Dr/Pembina Hw
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Late May 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Carlyle By - Westwood Dr / Westwood Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Cass St - Musgrove St / Barker Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Chancellor Dr - Augusta Dr / Markham Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Chancellor Dr - Augusta Dr / Quincy By
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 1,2023
Estimated to end
Early June 2023
Approx. % completed
50
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Chancellor Dr - Lakepointe Rd / Augusta Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Channing St - Wendon By / Burrows Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Charter Dr - Benbow Rd / Egesz St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 31, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Cherwell Rd - Beaverhill Bv / Bluewater Cr N leg
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Clare Av - Eccles St / Fisher St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Clare Av - Fisher St / Casey St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Clerkenwell By - Aldgate Rd/Aldgate Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
College Av - Salter St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Collegiate St - St Matthews Av / Silver Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Consulate Rd - Ambassador Rw / Diplomat Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Creek Bend Road Bridge Replacement
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Cumberland Av/Sargent Av - Furby St/Sherbrook St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Cuthbertson Av - Park Bv N / Bower Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Dagmar St - Bannatyne Av / McDermot Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Dagmar St - William Av / Bannatyne Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Dakota St - Beliveau Rd / St Marys Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Dakota St - Bishop Grandin Bv / Beliveau Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Darling St - Oakwood Av / Baltimore Rd
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
August 17, 2022
Estimated to end
Summer 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Document
+
De La Cathedrale Av/Hamel Av - Des Meurons St/De La Morenie St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
De Leglise Av - Campeau St / Pembina Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 30, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
De Leglise Av - St Pierre St / Campeau St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Deepwood Cv - Fernbank Av / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Des Meurons St - Goulet St / Marion St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2023
Estimated to end
October 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Dorset St - Manitoba Av / Pritchard Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Dowker Av/Fletcher Cr - Fletcher Cr/Pembina Hw
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Dugald Rd - Panet Rd / Dawson Rd N
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Dunkirk Pl - Kingston Rw / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Eccles St - Arnold Av / Morley Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Edmonton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Ellice Av - Colony St / Kennedy St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Erin St - Notre Dame Ave / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 1, 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Erin St - Sargent Av / Wolever Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 24,2022
Estimated to end
Fall 2023
Approx. % completed
40
Consultant
Morrison Hershfield Limited
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Exmouth Bv - Aldershot Bv / Holdsworth Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Fairlane Av - Isbister St / Buchanan Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Fallbrook By - Pebble Beach Rd / Pebble Beach Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Fernwood Av - St Annes Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 17, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Fifth Av/Guay Av - Des Meurons St/St Marys Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
+
Figaro St - Herbert Av / Talbot Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Fisher St - Arnold Av / Morley Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Fisher St - Montgomery Av / Churchill Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Fisher St - Morley Av / Oakwood Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Flamingo Av- Athlone Dr/Sturgeon Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Foster St - Manhattan Av/Beach Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Furby St - Portage Av / Broadway
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Galt Av - Duncan St / Lily St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Garden Grove Dr - Fairgrove By / Fairgrove By
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Gatineau By - Crestwood Cr / Crestwood Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 15, 2023
Estimated to end
Mid June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Glenthorne Cr - Greendell Av / Darwin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
June 7, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Glenthorne Cr - Woodlawn Av / Greendell Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
June 7, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Goulet St - Traverse Av / Youville St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 2023
Estimated to end
October 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Additional information
Click here
Document
+
Grandmont Bv - Co Op Entrance/ 40m West
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Grandmont Bv - Delorme By / East P/L of 96 Grandmont Bv
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Grandmont Bv - Gravel Pathway / Delorme Pl
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Grandmont Bv - Le Maire St / Retention Pond
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Grant Av - 150m East of Kenaston / Borebank St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Document
+
Grant Av - Borebank St / Montrose St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Late August 2023
Approx. % completed
80
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Document
+
Grassie Bv - Lagimodiere Bv / Molson St
View Map
Facility type
Street
Type of work
Reconstruction
+
Greencrest Av - Ulster St / Pembina Hw
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
Greenwood Pl - Portage Av / Wolseley Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Groverdale Av - Burdick Pl / Garden Grove Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
Facility type
Park
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Harrogate By - Hunterspoint Rd / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Harrow St - Academy Rd / Dromore Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Harrow St - Academy Rd / Kingsway
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Hartford Av - CPR Winnipeg Beach / Montcalm Cr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 5, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Hartford Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Fall 2024
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Hartford Av - McGregor St / Salter St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2024
Estimated to end
Fall 2024
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Hartford Av - Sinclair St / Montcalm Cr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 5, 2023
Estimated to end
Mid July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Harvest Ln - Valley View Dr / Heritage Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Hayes St - Whiteshell Av / McMeans Av W
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Hazel Dell Av - Brazier St / Henderson Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Heaton Av - Waterfront Dr / Argyle St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Helmsdale Av - Brazier St / Henderson Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Herbert Av - Figaro St / Chester St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Holdsworth Av - Glastonbury Bv / Aldershot Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Horace St - Des Meurons St / Enfield Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 8, 2023
Estimated to end
Late May 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Horace St - Youville St / Des Meurons St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 8, 2023
Estimated to end
Late May 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Horetzky St - Sanford Fleming Rd / Meadow Gate Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Inkster Bv - McKenzie St / Arlington St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Jackson Av- Stafford St/Harrow St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Jewett By - Sinnott St / Sinnott St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 26, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Johnson Av W - Levis St / Henderson Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Additional information
Click here
+
Jubilee Av - Cockburn St S / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Late October 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Kavanagh St/Giroux St - Dufresne Av/West Concrete Lane Limit
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 9, 2023
Estimated to end
Mid August 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Asphaltec Paving
Document
+
Keewatin St - Burrows Av/Gallagher Av W
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
To Be Determined
Estimated to end
To Be Determined
+
King Edward St and Park Lane Av Sidewalk (East Side)
View Map
Facility type
Sidewalk
Type of work
New Construction
Estimated to start
May 15, 2023
Estimated to end
Mid June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
King Edward St and Park Lane Av Sidewalk (East Side)
View Map
Facility type
Sidewalk
Type of work
New Construction
Estimated to start
May 15, 2023
Estimated to end
Mid June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Kirby Dr - Ness Av / Setter St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
La Barriere St - De Leglise Av / St Therese Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
La Grave St - Lemay Av / Lord Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 30, 2023
Estimated to end
Mid June 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lagimodiere Bv - Fermor Av / Cottonwood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Lagimodiere Bv - Island Shore Bv / Lagimodiere Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Lagimodiere Bv - Warman Rd/Dugald Rd
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Lake Green Pl - Lake Lindero Rd / Lake Lindero Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lake Linnet Pl - Lake Lindero Rd / Lake Lindero Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Lakeshore Rd - Chancellor Dr / Chancellor Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 5, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Langside St - Cumberland Av / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
August 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Larche Av W - Winona St / Transcona Trail
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Consultant
WSP Canada Inc
+
Larkin Cv - Brentlawn Bv / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Le Maire St - Grandmont Bv / Hydrant
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Linacre Rd - Radcliffe Rd / Michigan Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Linden Av - Brazier St / Henderson Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Linden Av - Roch St / Brazier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Logan Av - Dee St / Keewatin St
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Tetra Tech
Document
+
Logan Av - Disraeli Fwy / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Lumsden Av - Lake Ridge Rd / Cavalier Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Lyndale Drive Erosion Protection and Pathway Upgrades - Highfield St/Birchdale Ave
View Map
Facility type
Pedestrian / Cycling
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Macalester By - Silverstone Av / Silverstone Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
MacDonald Av - Gomez St / Waterfront Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Machray Av - Salter St / Powers St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Madrigal Cs - Marquis Cr/Mapleton Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Magdalene By - Baylor Av / Baylor Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Manahan Av - Pembina Hw / Hudson St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Mandan Rd - Herron Rd / Mariner Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Maplegrove Rd - Maplegrove Rd / Maplegrove Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Markham Rd - Chancellor Dr (E) / Forest Lake Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Mazenod Rd - De Baets St / Dugald Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Mazenod Rd - Dugald Rd / Paquin Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
McDermot Av - McPhillips St / Myrtle St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
McGregor St - Church Av / Mountain Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McGregor St - Seven Oaks Av / McAdam Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
McMicken St - Cumberland Av / Sargent Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
McMillan Av/Corydon Av/Donald St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Early September 2022
Estimated to end
Summer 2023
Approx. % completed
50
Consultant
City Of Winnipeg - Streets Maintenance Division
Document
+
McPhillips St - Machray Av / Mountain Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
+
Midland St - Notre Dame Av / Saskatchewan Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Midwinter Av - Stadacona St / 193 Midwinter Ave
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Streets Maintenance Division
+
Moberly Av - Sanford Fleming Rd / Cambie Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Moberly Av - Whiteway Rd / Sanford Fleming Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Montrose St - Grant Av / Mathers Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Moore Av - Dunkirk Dr / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 1, 2022
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - Flynn St / Pulberry St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 1, 2022
Estimated to end
Late June 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - Pulberry St / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 1, 2022
Estimated to end
Late June 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Moore Av - River Rd / Flynn St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 1, 2022
Estimated to end
Late June 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
JC Paving
Document
+
Morrow Av - St Annes Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 29, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Mountain Ave - Arlington St / Airlies St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 1, 2023
Estimated to end
Late August 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Document
+
Musgrove St - Cass St / Barker Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Norfolk Av - Kingston Rw / Oakcrest Pl
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Leila Av / Church Av
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
September 14, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
City Of Winnipeg - Engineering Division
Contractor
Wintec Building Services Inc.
Document
+
Norwood & Main Street Bridge Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
+
Notre Dame St - Langevin St / St Joseph St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 8, 2023
Estimated to end
Late May 2023
Approx. % completed
5
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Nugent Rd - Hatcher Rd / Rougeau Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Oakcrest Pl - End / Dunkirk Pl
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Oakdale Dr - Coy Av / Grant Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Oakenwald Av - Wicklow St / Pembina Hw
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Oakview Av - Brazier St / Henderson Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Oakwood Av - Eccles St / Darling St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Osborne St - Stradbrook Av / Wardlaw Av
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Pacific Av - Arlington St / Xante St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Pacific Av - Xante St / McPhillips St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Palmerston Av - Arlington St / Ethelbert St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Mid August 2023
Approx. % completed
50
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Pandora Av E - 645 Pandora Av E / Wayoata St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Pandora Av E - Brelade St / 645 Pandora Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Pandora Av E - Ravenhurst St / Brelade St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Pandora Ave E - Redonda St / Wayoata St
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
July 4, 2022
Estimated to end
Summer 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Panet Rd - Abandoned Railway X-ing / Marion St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Panet Rd - Dugald Rd/ Abandoned Railway X-ing
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Panet Rd - Regent Av W / Mission St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Panet Rd Pathway - Reenders Dr/Talbot Av
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
September 26, 2022
Estimated to end
Summer 2023
Approx. % completed
50
Consultant
City Of Winnipeg - Engineering Division
Document
+
Peake Av - Robson St / Plessis Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Pembina Hw - McGillivray Bv / Chevrier Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 8, 2023
Estimated to end
Late October 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Pipeline Rd - North of Templeton Av to South of Storie Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 1, 2023
Estimated to end
Late June 2023
+
Plessis Rd - Devonshire Dr / Gunn Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
May 15,2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Powers St - Cathedral Av / Machray Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Pritchard Av - Chudley St / Keewatin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
June 5, 2023
Estimated to end
Early July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Pritchard Av - Main St / Charles St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 5, 2023
Estimated to end
Early July 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Pritchard Av - Powers St / Charles St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
June 5, 2023
Estimated to end
Early July 2023
Approx. % completed
Planned
Document
+
Pritchard Av - Powers St / McKenzie St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 5, 2023
Estimated to end
Early July 2023
Approx. % completed
Planned
Document
+
Radburn Pl - End / Beaverhill Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Raleigh St - Glenway Av / Gilmore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Ravine Dr - River Pointe Dr / Settlers Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
May 10, 2023
Estimated to end
Early June 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Redwood Av - Salter St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
August 2022
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group Limited
Document
+
Reenders Pathway - Stapon Rd/Panet Rd
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
September 26, 2022
Estimated to end
Summer 2023
Approx. % completed
50
Consultant
City Of Winnipeg - Engineering Division
Document
+
Reenders Pathway - Stapon Rd/Panet Rd
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
September 26, 2022
Estimated to end
Summer 2023
Approx. % completed
50
Consultant
City Of Winnipeg - Engineering Division
Document
+
Refinery District BRT Pathway Connection
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Regal Av - Des Meurons St / St Annes Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 17, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Renfrew St - Grant Av / Taylor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 29, 2022
Estimated to end
Spring 2023
Approx. % completed
80
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Renfrew St - John Brebeuf Pl / Grant Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
River Av - Osborne St / Wellington Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2023
Estimated to end
Late October 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Roblin Bv - Grant Av / William R Clement Pw
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Roblin Bv - William R Clement Pw / Roblin Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Ross Av - King Edward St/Oddy St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Rossmere Cr - Dunvegan St / Kildonan Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
September 23, 2022
Estimated to end
Summer 2023
Approx. % completed
90
Consultant
KGS Group Limited
Contractor
Wintec Building Services Inc.
Document
+
Route 90 Culvert at Omand's Creek
View Map
Facility type
Bridge
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
0
Consultant
Morrison Hershfield Limited
+
Royal Salinger Rd - Niakwa Rd / Pebble Beach Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Salter St - Jefferson Av / Inkster Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Sargent Av - Balmoral St / Edmonton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av - Furby St / Balmoral St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av/Ellice Av - Clifton St/Spruce St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 8, 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Contractor
Darco Enterprises
Document
+
Sargent Av/Ellice Av - Furby St/Sherbrook St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Saskatchewan Av - King Edward St / Century St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Summer 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Saskatchewan Av - King Edward St / Sherwin Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 18, 2022
Estimated to end
Summer 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Saskatchewan Av - Midland St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Saskatchewan Av - St James St / Border St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 18, 2022
Estimated to end
Summer 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
+
Scotland Av - Harrow St / Stafford St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Scotland Av - Harrow St / Wilton St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Scurfield Bv - Kenaston Bv / Henlow By
View Map
Facility type
Sidewalk
Type of work
New Facility
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Seabrook Cv - Beaverhill Bv / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Selkirk Av - Main St / Salter St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Document
+
Selkirk Ave - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Spring 2023
Approx. % completed
90
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Shields St - Moberly Av / Sanford Fleming Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Sinnott St - Barker Bv / Barker Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
+
Smith - Graham Av/Midtown Bridge
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 23, 2023
Estimated to end
July 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Ellice Av / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 23, 2023
Estimated to end
July 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Notre Dame / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 23, 2023
Estimated to end
July 2023
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Smith St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 23, 2023
Estimated to end
July 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Maple Leaf Construction Ltd.
Additional information
Click here
Document
+
Sparrow Rd - Roblin Bv / 46 Sparrow Rd
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Sprague St - Portage Av / Wolseley Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 5, 2023
Estimated to end
August 2023
Approx. % completed
Planned
Consultant
Dillon Consulting Limited
Document
+
Springfield Rd - Cox Bv / Lagimodiere Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
St Annes Rd - Hindley Av/Worthington Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2022
Estimated to end
Fall 2023
Approx. % completed
Planned
Document
+
St Thomas Rd - End / Fermor Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Facility type
Street
Type of work
Rehabilitation
Estimated to start
March 1, 2023
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
St. James Bridges Minor Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Winter 2022
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Tetra Tech
+
St. Mary's Road Riverbank Stability
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Stafford St - Scotland Av/Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2023
Estimated to end
Fall 2023
Approx. % completed
10
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
+
Sterling Lyon Pw - Victor Lewis Dr/Kenaston Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Sterling Lyon Pw - Victor Lewis Dr/Kenaston Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Stillwater Rd - Brookhaven By / Willowlake Cr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Stradbrook Av - Queen Elizabeth Wy/Harkness St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
June 2023
Estimated to end
August 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Stradbrook Ave - Wellington Cr / Osborne St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2023
Estimated to end
Late October 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
Summerside Av - Caledon Rd / End
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Tahoe By - Lakewood Bv / Lakewood Bv
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Taylor Ave - Harrow St / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 2022
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Stantec Consulting Ltd
Contractor
Nelson River Construction
Additional information
Click here
Document
+
Tulane By - Pasadena Av / Pasadena Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
+
University Cr - Pembina Hw / Thatcher Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 15, 2023
Estimated to end
July 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Document
+
University Cr - Thatcher Dr / Pembina Hw
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
July 2023
Approx. % completed
70
Consultant
AECOM Canada Ltd
Contractor
Bituminex Paving Ltd
Document
+
Victoria Av E - Roanoke St / Leola St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 8, 2023
Estimated to end
Early June 2023
Approx. % completed
80
Consultant
WSP Canada Inc.
Contractor
Bayview Construction Ltd
Document
+
Wall St - Wellington Av / Notre Dame Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 16,2022
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
Contractor
J.C. Paving Ltd.
Additional information
Click here
Document
+
Waller Av/Clarence Av - Hudson St/Marshall Cr
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
May 23, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
KGS Group Limited
Contractor
Bayview Construction Ltd
Document
+
Warde Av - 337 Warde Ave / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Warde Av - Dakota St / John Forsyth Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Warde Av - John Forsyth Rd / 337 Warde Ave
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc.
+
Wardlaw Av - Nassau St N / Daly St N
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Warsaw Av - Cockburn St N / Lilac St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Warsaw Av - Hugo St N / Cockburn St N
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Watson St - Leila Av / Jefferson Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2023
Estimated to end
Fall 2023
Consultant
City Of Winnipeg - Engineering Division
Document
+
Waverley St - Cadboro Rd / 165m South of Cadboro Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
KGS Group
Document
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Wellington Cr - River Av / Stradbrook Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
June 2023
Estimated to end
Late October 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc.
Document
+
West Fernwood Av - Bronstone Bv / Dunkirk Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
West Fernwood Av - Bronstone Bv / St Marys Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Whiteshell Av - McMeans Av W / Winona St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Wildwood G Pk - South Dr / Wildwood St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Wildwood H Pk - South Dr / South Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Wilkes Av - Victor Lewis Dr/Waverley St
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
June 2023
Estimated to end
August 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Wilkes Av - Waverley St / Wilkes Av
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
June 2023
Estimated to end
August 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
William Av - Arlington St / McPhillips St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2022
Estimated to end
Summer 2023
Approx. % completed
80
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
William Av - Main St / King St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
Winona St - Larche Av W / McMeans Av W
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Woodchester By - Cathcart St/Cathcart St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Woodford By - Meadowood Dr / Meadowood Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Fall 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Wyatt Rd - Filkow By / Inkster Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 29, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Wyatt Rd - Mandalay Dr / Filkow By
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 29, 2023
Estimated to end
Late July 2023
Approx. % completed
Planned
Consultant
WSP Canada Inc
Document
+
Wynford Dr - St Martin Bv / Ainsdale Wy
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wynford Dr - St Martin Bv / Ainsdale Wy
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Late June 2023
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Document
+
York Av - Main St / Carlton St
View Map
Facility type
Sidewalk
Type of work
Reconstruction
Estimated to start
May 15, 2023
Estimated to end
Late June 2023
Approx. % completed
0
Consultant
City Of Winnipeg - Engineering Division
Document
+
Yukon Av - Milt Stegall Dr / St James St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 24, 2022
Estimated to end
Summer 2023
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Document
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.