Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links

Thanksgiving – Monday, October 14. View holiday hours for City of Winnipeg facilities and services.

Thanksgiving – Monday, October 14. View holiday hours for City of Winnipeg facilities and services.

Public Works

Ness Avenue at Sturgeon Creek Culvert Replacement

This project is now complete.

Project Update – April 2018

Construction of the Ness Avenue Bridge over Sturgeon Creek and associated Roadworks on Ness Avenue was substantially completed in the fall of 2016, with the roadway opening to pedestrians and traffic in October 2016. Outstanding seasonal deficiencies such as landscaping were completed over the summer of 2017.

Project Update – June 2017

Construction continues and expected to the completed later this summer.

Project Update – September 01, 2016

Construction is on schedule with completion expected in October 2016. All components of the new bridge are complete, its approaches and under-bridge paths are currently being built. Roadwork on the East side of the new bridge, between Valley View Drive and Pebblewood Lane, is complete. Roadwork on the West side of the new bridge, between School Road and Wharton Boulevard, is ongoing.

Traffic flows through and around the area appear to still be working well. The round-about at Sturgeon Road at Silver Avenue was opened in July 2016. The no right-turn restriction from Hamilton Avenue to Valley View Place during peak morning rush hours of 7:00 am to 9:00 am has been removed. Winnipeg Transit buses 24 Ness Express and 25 Ness Super Express are no longer rerouted via Sturgeon Road, Portage Avenue, and School Road. These Winnipeg Transit buses are now on route via Sturgeon Road, Silver Avenue, Hamilton Avenue, and Vimy Road (Eastbound) or Parkhill Street (Westbound).

The City of Winnipeg thanks residents for its patience while construction is underway, which is expected to be complete by the end of October, 2016.

Photos for project update: Photo 1 | Photo 2 | Photo 3

Project Description:

The existing Ness Avenue at Sturgeon Creek culvert will be replaced with a new high level bridge with a 75 year lifespan. This will:

  • improve safety and functionality;
  • prevent roadway flooding;
  • provide bank stability and protect against erosion;
  • improve active transportation through the site;
  • improve surrounding roadways through reconstruction and rehabilitation;

Project Update – February 22, 2016:

Construction is underway and is on schedule. Foundations for the new bridge have been installed and concrete substructure work, in-stream work, and sewer outfall work is ongoing.

After the initial acclimatization phase, traffic flows through and around the area appears to be working well. To maintain safety on Valley View Drive, a no right turn restriction from Hamilton Avenue to Valley View Place during peak morning rush hours of 7:00 am to 9:00 am has been installed.

The opening of Silver Avenue eastbound from Hamilton Avenue to Sturgeon Road is delayed due to required Manitoba Hydro relocations of poles at the Sturgeon Road and Silver Avenue roundabout. Hydro pole relocation work has just started. Expected completion of the relocation and opening of Silver Avenue eastbound from Hamilton Avenue to Sturgeon Road is in May 2016.

Due to this delay in the commencement of the Hydro installations for the roundabout, the 24 Ness Express and 25 Ness Super Express will continue to reroute via Sturgeon Road, Portage Avenue, and School Road. The reroute will continue to be in place in the coming months until the Hydro work is completed and Silver Avenue can be fully opened from Hamilton Avenue to Sturgeon Road. We apologize for the inconvenience.

The City of Winnipeg thanks residents for its patience while construction is underway.

Project Update – December 1, 2015:

Construction to begin in early December 2015

The Ness Avenue over Sturgeon Creek bridge construction project will begin in early December 2015. As a result, Ness Avenue between School Road and Valley View Drive will be closed from December 2015 to October 2016. Ness Avenue between Valley View Drive and Heritage Boulevard will be closed to vehicular traffic beginning in spring 2016, and Ness Avenue between Wharton Boulevard and School Road, and between Heritage Boulevard and Pebblewood Lane will be limited to one lane of staged traffic beginning in spring 2016. Please see the traffic staging plan for more information.

Winter construction allows creek, embankment and bridge foundation works to be completed prior to the "no in-stream work period" in the spring and minimizes the construction schedule. Bridge superstructure concrete works, road works, and sewer and water renewals will be completed over the summer and early fall.

Transit routes #24 and #25 will be rerouted. Buses on Ness Avenue will use Sturgeon Road, Portage Avenue, and School Road until the roundabout at Sturgeon Road and Silver Avenue is open. For the duration of the project buses will use Sturgeon Road, Silver Avenue, Hamilton Avenue, and Vimy Road (Eastbound)/Parkhill Street (Westbound). Please see the transit re-route maps for additional information: Dec 2015 to Feb 2016 | Feb 2016 to Oct 2016

The Sturgeon Creek Greenway Trail paths on the west bank of Sturgeon Creek will be closed north and south of the construction site.

Construction work will be carried out between the hours of 7:00 a.m. and 10:00 p.m. Monday to Friday and as required between 9:00 a.m. and 9:00 p.m. on Saturdays, Sundays or holidays.

The City of Winnipeg realizes that the construction work will be disruptive and we will endeavor to complete the work as quickly and efficiently as possible. We thank citizens for their patience.

Repairs to select existing streets

Minor needed repairs were carried out in October 2015 on School Road between Portage Avenue and Ness Avenue, and on Vimy Street and Parkhill Street between Ness Avenue and Hamilton Avenue in preparation for the upcoming bridge construction. It is anticipated that slightly increased traffic levels will occur on those streets because of traffic and transit detours.

Local traffic study

In spring of 2015, local traffic counts were taken in the area to confirm whether modifications to the existing traffic controls are required. Currently there is a 2-way stop sign at Ness and School Road and a pedestrian crossing west of the intersection. Following analysis, it was confirmed that these traffic controls are appropriate.

Project Update - September 9, 2015:

Land Drainage Sewer "Sink Hole" at the Southwest Corner of the Bridge

A land drainage sewer "sink hole" opened up on Friday, September 4, 2015, southwest of the bridge at one of the land drainage sewer outfalls, eroding the ground. The outfall pipes were in poor condition and are slated to be replaced as part of the upcoming bridge construction. A "sink hole" is created when a gap in the pipe allows rain water to enter and erode soils surrounding the pipe until the surface collapses. Ness Avenue between School Road and Valley View has been closed until repairs are completed. Repairs to restore conditions and open Ness Avenue will be undertaken by the Water and Waste Department and will be completed as quickly as possible.

Public Information Session:

A Public Information Session was held January 13, 2015.

The open house display boards show information about the project including:

  • Traffic in the area;
  • Potential detours;
  • Access during construction;
  • Transit detours;
  • Project timelines;
  • Environment impacts.
Ness Avenue at Sturgeon Creek Culvert Replacement
Last update: November 8, 2019

Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.