Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on January 18, 2026 @ 2:30 PM)
 
 


Abinojii Mikanah (WB) - Dakota St / St Marys Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Abinojii Mikanah WB to Pembina Hw NB   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Academy Rd / Kingsway - Oak St / Ash St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Addington By - Oakdale Dr / End   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Addington By - Oakdale Dr / End   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Adsum Dr / Sasaki Cr - Sorokin St / Sasaki Cr   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Alenbrook By - Alenbrook By / End   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Arlington St - Enniskillen Av / Lansdowne Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Arlington St - Lansdowne Av / Inkster Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Assiniboine Park Pedestrian Bridge   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2025
Approx. % completed 0
Austin St - Higgins Av / Henry Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bannatyne Av / McDermot Av - Tecumseh St / Arlington St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Barry Av - Plessis Rd / Robson St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bayne Cr / London St - Bayne Cr / Tu Pelo Av   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bayview Pl - Paulley Dr / McMeans Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 21, 2025
Estimated to end Summer 2026
Approx. % completed 80
Consultant WSP Canada Inc
Document
2025 Construction Notice - Bayview Place.pdf
Beaverhill Bv - Beaverhill Bv / Beaverhill Bv   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beaverhill Bv - Fermor Av / Park Terrace Dr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beaverhill Bv - Park Terrace Dr / Fermor Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beaverhill Bv - Park Terrace Dr / Shamrock Dr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Beecher Av / Templeton Av - Brambleberry Pl / Garden Park Dr   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Beeston Dr - Seaforth Av / Seaforth Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Beliveau Rd - Kearney St / Dakota St   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bellavista Cr - Voyageur Av / Rogan Dr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Berrydale Av - End / St Annes Rd   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Blanchard Av - Middle Gate / West Gate   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed 0
Consultant Tetra Tech
Document
2025 Construction Notice_ Armstrongs Point(FRONTING CONSTRUCTION).pdf
Boston Av - Morley Av / Hudson St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bradford St - Saskatchewan Av / Wellington Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Brock St - Grant Av / Mathers Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St   View Map
Facility type Alley
Type of work Renewal
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St   View Map
Facility type Alley
Type of work Renewal
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St   View Map
Facility type Alley
Type of work Renewal
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Bury St - Whyte Av / Irysh Av   View Map
Facility type Street
Type of work TBO
Estimated to start July 14, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Bury St.pdf
Bushnell St - Logan Av / Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Carlaw Av - Nassau St S / Daly St S   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Carlton St - Cumberland Av / Notre Dame Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Carlton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Carlton St - Graham Av / St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Carlton St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Carlton St - York Av / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Carrigan Pl - Ulster St / Lane   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Carruthers Av - Cottingham St / 1037 Lansdowne Ave   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Carter Av - Pembina Hw / Lilac St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2026
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Preconstruction Notice - Carter Ave.pdf
Chancellor Dr - Markham Rd / Path   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Charles St - Jarvis Av / Sutherland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises
Chatham Pl - Morningside Dr / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 11, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Construction Notice_Chatham Pl.pdf
Chopin Bv - Wiebes Dr / Uxbridge Rd N   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cora Av - Whitegates Cr / Maureen St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Crescent Dr - 758 Crescent Dr / Pembina Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Crowson By - Dowker Av / Dowker Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Day St - Kildare Av E / Victoria Av E   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Day St - Regent Av E / Victoria Av E   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Day St - Victoria Av E / Regent Av E   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dells Cr - Wales Av / Hazelwood Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Denton Pl - End / Grant Av   View Map
Facility type Street
Type of work Overlay
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Devonshire Dr / Whiteway Rd - Clouston Dr / Sanford Fleming Rd   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dubois Pl/Champagne Cr - Champagne Cr/Lamirande Pl   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dufferin Av - Powers St / McGregor St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Dzyndra Cr - Hatcher Rd / Bournais Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 10, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Document
2025 Construction Notice - Dzyndra Crescent.pdf
East Gate - Blanchard Av / Middle Gate   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant Tetra Tech
Document
2025 Construction Notice_ Armstrongs Point(FRONTING CONSTRUCTION).pdf
Edmonton St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Edmonton St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed Planned
Consultant AECOM Canada Ltd
Edmonton St - Graham Av / St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Edmonton St - St Mary Av / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Elgin Av - Isabel St / Sherbrook St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 21, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Elgin Ave.pdf
Elgin Av W - Worth St / Keewatin St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
English Pl - Darwin St / Darwin St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Garbage Hill   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ghent Cv - Mayfield Cr / Mayfield Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 2, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Document
2025 Construction Notice_Ghent Cove.pdf
Glen Av - Killarney St / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Golf Bv - McBey Av / Meadowside Dr   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Goulding St - Ellice Av / St Matthews Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Goulding St - Sargent Av / Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Goulding St - Wolever Av / Portage Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grant Av - Harrow St / Grant Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grant Av - Wilton St / Grant Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Greenacre Bv - Portage Av / McBey Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Greenlea Cv - Gilmore Av / Gilmore Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grosvenor Av / Corydon Av - Cordova St / Campbell St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Gunnell St - Henry Av / Logan Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harbour View Access   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harbour View Access   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harbour View Access   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hargrave St - Cumberland Av / Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Hargrave St - Ellice Av / Cumberland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Hargrave St - Graham Av / St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Harriet St - Bannatyne Av / McDermot Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harriet St - McDermot Av / Notre Dame Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hector Av E - Lilac St / Wentworth St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2025
Estimated to end Summer 2026
Approx. % completed 10
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Preconstruction Notice - Hector Ave E.pdf
Hector Av W - Wentworth St / Stafford St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2025
Estimated to end Summer 2026
Approx. % completed 10
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Preconstruction Notice - Hector Ave W.pdf
Helmsdale Av / Kimberly Av - Raleigh St / Golspie St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henry Av - Gunnell St / Sherbrook St   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Huntleigh St - St Matthews Av / Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant KGS Group
Irysh Av - Bury St / Blake St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 14, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Irysh Ave.pdf
Jarvis Av - Andrews St / McGregor St   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Jarvis Av - McGregor St / McKenzie St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Jarvis Av - McKenzie St / Parr St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Jarvis Av - Powers St / Andrews St   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Johnson Av E - Grey St / Gateway Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kate St - Elgin Av / William Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 21,2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Kate St.pdf
Kennedy St - St Mary Av / York Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kennedy St - York Av / Broadway   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kennedy St - Ellice Av / Qu'Appelle Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kennedy St - Graham Av / St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kennedy St - Portage Av / Graham Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kennedy St - Qu'Appelle Av / Cumberland Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Kenneth St - Dowker Av / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kent Rd - Beach Av / Talbot Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kent Rd - Keenleyside St / Chalmers Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kent Rd - Talbot Av / Nairn Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kilmer Av - Carroll Rd / Longfellow By   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kings Dr - Silverstone Av / Kilkenny Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kings Dr - U of M Campus / Silverstone Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kings Park Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kingsway / Grosvenor Av - Lindsay St / Railway Tracks   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
La Porte Pl/Le Maire St - La Porte Pl/Le Maire St   View Map
Facility type Alley
Type of work Asphalt Overlay
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Almey Av / CNR Overpass   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - CNR Overpass / Grassie Bv   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Concordia Av E / Lagimodiere Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Grassie Bv / CNR Overpass   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv Overpass over CPR Keewatin   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Leila Ave - McPhillips St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Bayview Construction Ltd
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lindenwood Dr W - Lindenwood Dr W / Lindenwood Dr W   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lindenwood Dr W - Lindenwood Dr W / Lindenwood Dr W   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Litz Pl - Henderson Hw / Appleton St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lodge / Portage Av - Wallasey St / Thompson Dr   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lodge Av / Portage Av - Aldine St / Wallasey St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lodge Av / Portage Av - Vernon Rd / Whytewold Rd   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lodge Av / Portage Av - Whytewold Rd / Olive St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av - Omands Creek Bv / Brookside Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
London St / McCreedy Rd - Amelia Cr / Tu Pelo Av   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Manhattan Av - Stapleton St / Keenleyside St   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Marcus Pl - Whiteway Rd / End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 18, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Document
2025 Construction Notice_Marcus Place.pdf
Marigold By - Sinclair St / Sinclair St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Marshall Cr - Waller Av / Clarence Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 30, 2025
Estimated to end Summer 2026
Approx. % completed 80
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Construction Notice - Marshall Cr.pdf
Martha St - Henry Av / Logan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McDermot Av / Notre Dame Av - Notre Dame Av / Tecumseh St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McDermot Av / Notre Dame Av - Princess St / Adelaide St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McFarlane St N - Rover Av / Sutherland Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 15, 2025
Estimated to end Summer 2026
Approx. % completed 80
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - McFarlane St N .pdf
McGregor St - Selkirk Av / Dufferin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McKelvey St - End / Logan Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McKenzie St - Hartford Av / Jefferson Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McKenzie St - Kingsbury Av / Hartford Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McMicken St - Sargent Av / Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start June 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Document
2025 Construction Notice_McMicken St.pdf
McMillan Av / Corydon Av - Hugo St N / Cockburn St N   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McMullen Cr - Hatcher Rd / Hatcher Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 10, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Document
2025 Construction Notice - McMullen Crescent.pdf
McPhillips St - Emes Rd / North Point Bv   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Middle Gate - Cornish Av / East Gate   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 80
Consultant Tetra Tech
Document
2025 Construction Notice_ Armstrongs Point(FRONTING CONSTRUCTION).pdf
Midtown Bridge   View Map
Facility type Bridge
Type of work Maintenance
Estimated to start August 2025
Estimated to end Summer 2026
Approx. % completed 80
Document
2025 Construction Notice_Midtown Bridge.pdf
Nassau St S - Brandon Av / Hethrington Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Nassau St S - Hethrington Av / Morley Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Nolin Av/Nolin Av - Dubois Pl/Nolin Av   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Nolin Av/Nolin Av - Dubois Pl/Nolin Av   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2026
Estimated to end Fall 2027
Approx. % completed Planned
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2026
Estimated to end Fall 2027
Approx. % completed Planned
Osborne 160   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed 0
Consultant Barnes and Duncan
Document
2024 Construction Notice_160 Osborne St.pdf
Osborne St - Baltimore Rd / Rosedale Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Stantec Consulting Ltd
Osborne St - Rosedale Av / St Vital Bridge   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Stantec Consulting Ltd
Osborne St/Nassau St S - Kylemore Av/Walker Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Construction Notice_Walker_Rathgar.pdf
Osborne St/Nassau St S - Walker Av/Rathgar Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Construction Notice_Walker_Rathgar.pdf
Panet Rd - Nairn Av / CPR TRacks   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Parker Av - Daniel St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Parker Av - Derek St / Daniel St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Parker Av - Wynne St / Derek St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Parkville Dr - Dunkirk Dr / Pulberry St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Paufeld Dr - Karen St / Rothesay St   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Paulley Dr - Redonda St / Dowling Av E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 21, 2025
Estimated to end Summer 2026
Approx. % completed 80
Consultant WSP Canada Inc
Document
2025 Construction Notice - Paulley Drive.pdf
Peacock Pl - End / Lake Grove By   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Highway Bridge over Abinojii Mikanah Rehabilitation   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 10
Document
2025 Preconstruction Notice - Pembina Overpass.pdf
Pembina Hw NB to Abinojii Mikanah EB   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Spring 2026
Estimated to end Fall 2026
Approx. % completed Planned
Pembina Hw NB to Abinojii Mikanah WB   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Spring 2026
Estimated to end Fall 2026
Approx. % completed Planned
Document
2025 Preconstruction Notice - Pembina Overpass.pdf
Pembina Hw SB to Abinojii Mikanah EB   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 10
Document
2025 Preconstruction Notice - Pembina Overpass.pdf
Pembina Hw SB to Abinojii Mikanah WB   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 10
Document
2025 Preconstruction Notice - Pembina Overpass.pdf
Perth Av - McGregor St / Parr St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Plessis Rd - 560 Plessis Rd / St Boniface Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Plessis Rd - 996 Plessis Rd / St Boniface Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Plessis Rd - St Boniface Rd / 560 Plessis Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Plumtree Pl - Meadowood Dr / Meadowood Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Poplynn Dr - Egesz St / Egesz St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Portage Av - Banting Dr / Sturgeon Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 28, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Document
2025 Construction Notice - Portage Ave.pdf
Portage Av - David St / Cavalier Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start July 28, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Document
2025 Construction Notice - Portage Ave.pdf
Portage Av - Sturgeon Rd / Cavalier Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start July 28, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant Stantec Consulting Ltd
Contractor Bayview Construction Ltd
Document
2025 Construction Notice - Portage Ave.pdf
Portage Av / Allard Av - Best St / Bedson St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av / Allard Av - Best St / Bedson St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av / Picardy Pl - Broadway / Canora St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Prince Edward St - Rover Av / Lane   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2026
Estimated to end Fall 2026
Approx. % completed Planned
Consultant KGS Group
Contractor JC Paving
Document
2025 Preconstruction Notice 1 - Prince Edward St.pdf
Qu'Appelle Av - Balmoral St / Kennedy St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Document
2025 Preconstruction Notice 1 - Qu'Appelle Ave.pdf
Radar Pl - Voyageur Av / Rogan Dr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Raquette St - Browning Bv / Assiniboine Av   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Regent Av E / Melrose Av E - Kanata St / Day St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rogan Dr - Bellavista Cr / Hamilton Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Roslyn Rd / River Av - Roslyn Rd / Nassau St N   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rosseau Av W / Ravelston Av W - Brewster St / Plessis Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rover Av - Angus St / Annabella St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rover Av - Barber St / Hallet St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rover Av - Disraeli St / Barber St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Rupert Av - Martha St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant AECOM Canada Ltd
Sage North Development Phase 1A Contract 5A   View Map
Facility type Street
Type of work New - Street Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sage North Development Phase 1A Contract 5C   View Map
Facility type Street
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sandralin By - End / Avalon Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent Av - Balmoral St / Edmonton St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Sargent Av - Furby St / Balmoral St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Sargent Av / Ellice Av - Downing St / Minto St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sawchuk By - Antrim Rd / Antrim Rd   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Scotia St - Armstrong Av/Newton Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Seaforth Av - Main St / Aikins St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Sherbrook St - Henry Av / Logan Av   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sims Cr - Hatcher Rd / Hatcher Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 10, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Document
2025 Construction Notice - Sims Crescent.pdf
St Anthony Av - Andrews St / McGregor St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
St Anthony Av - McGregor St / Parr St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
St Mary Av - Edmonton St / Memorial Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
St Marys Rd - Dakota St / Fermor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd - Fermor Av / West Fernwood Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd - Molgat Av / Moore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd - Moore Av / Arden Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd - PTH 100 / Chrypko Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd - West Fernwood Av / Molgat Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Matthews Av / Silver Av - Madison St / Kensington St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Matthews Av / Wolever Av - Strathcona St / Railway Tracks   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St. Vital Park   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St. Vital Park   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St. Vital Park   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sunglow Rd - Dawnville Dr / Kildonan Meadow Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sweetwood By - Forest Park Dr / Forest Park Dr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
University Cr - 80m North of Dysart Rd/Thatcher Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2026
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
Change in Access Notice_Blue Bomber Games FINAL.pdf
University Cr - Markham Rd / 80m North of Dysart Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2024
Estimated to end Summer 2026
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Additional information Click here
Document
Change in Access Notice_Blue Bomber Games FINAL.pdf
Waller Av - Pembina Hw / Lane West of Donnelly St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Spring 2026
Estimated to end Fall 2026
Approx. % completed Planned
Consultant WSP Canada Inc
Contractor Asphaltec Paving
Document
2025 Construction Notice - Waller Ave.pdf
Warren Pl - Amanda Cr / End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Waterbury Dr - Lindenwood Dr E / Lindenwood Dr E   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Weatherdon Av - Stafford St / Harrow St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
West Av - Rouge Rd / Whitegates Cr   View Map
Facility type Street
Type of work Major Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
West Gate - Blanchard Av / Middle Gate   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant Tetra Tech
Document
2025 Construction Notice_ Armstrongs Point(FRONTING CONSTRUCTION).pdf
Whiteway Rd - Clouston Dr / Sanford Fleming Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 18, 2025
Estimated to end Summer 2026
Approx. % completed 70
Consultant WSP Canada Inc
Document
2025 Construction Notice_Whiteway Road.pdf
Whyte Av - East of Vine St / Quelch St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 8, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Whyte.pdf
Whyte Av - Quelch St / Bury St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start September 8, 2025
Estimated to end Summer 2026
Approx. % completed 90
Consultant KGS Group
Contractor JC Paving
Document
2025 Construction Notice - Whyte.pdf
Wilkes Av - 400m W of Charleswood Rd / PTH 100   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Wilkes Av - Harstone Rd / 400m E of Charleswood Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Woodfield By / Woodfield By - Woodfield By / Cathcart St   View Map
Facility type Alley
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Yale Av W - Bond St / Winona St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Yale Av W - Day St / Bond St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
York Av - Carlton St / Kennedy St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
York Av - Kennedy St / Vaughan St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
York Av - Vaughan St / Memorial Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc
Zeglinski Cr - Wiebes Dr / Zeglinski Cr   View Map
Facility type Street
Type of work Minor Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.