Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links

Transit bus delays and cancellations possible beginning Monday, Nov 27. Check your bus schedule online before heading out.

 Traffic alert: Arlington Bridge is closed to all traffic indefinitely. Use McPhillips Street Underpass or Slaw Rebchuk Bridge (Salter Street) to cross rail yards.

Transit bus delays and cancellations possible beginning Monday, Nov 27. Check your bus schedule online before heading out.

 Traffic alert: Arlington Bridge is closed to all traffic indefinitely. Use McPhillips Street Underpass or Slaw Rebchuk Bridge (Salter Street) to cross rail yards.

Public Works

Road construction list

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format.

More information: Lane closures

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on November 29, 2023 @ 8:00 PM)
 
 


Ainsworth Pl - Kirkbridge Dr / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Archibald St - Messier St / Doucet St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Document
2023 Construction Notice_Archibald2.pdf
Archibald St - Plinguet St / Messier St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 23, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor To Be Determined
Additional information Click here
Document
2023 Construction Notice_Archibald2.pdf
Beaulynn Cv - Allendale Dr / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Beecher Av - Ferrier St / End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Global Homes
Broadway - Spence St / Sherbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start August 8, 2023
Estimated to end Summer 2024
Approx. % completed 75
Consultant City Of Winnipeg - Engineering Division
Contractor J&D Penner Ltd
Document
2023 Construction Notice_Broadway Sidewalk Renewal.pdf
Creek Bend Road Bridge Replacement   View Map
Facility type Bridge
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Fall 2024
Approx. % completed 30
Cumberland Av/Sargent Av - Furby St/Sherbrook St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Spring 2023
Estimated to end Summer 2024
Approx. % completed 70
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Preconstruction Notice_Alley_Sherbrook Street,Cumberland Avenue,Sargent Avenue,Furby Street.pdf
Dakota St - Beliveau Rd / St Marys Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 8,2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant Morrison Hershfield Limited
Contractor Wintec
Document
2023 Construction Notice_Dakota St2.pdf
Dakota St - Bishop Grandin Bv / Beliveau Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 8,2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant Morrison Hershfield Limited
Contractor Wintec
Document
2023 Construction Notice_Dakota St2.pdf
Fisher St - Arnold Av / Morley Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Oakwood Ave to Arnold Ave.pdf
Fisher St - Montgomery Av / Churchill Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Montgomery Ave to Churchill Drive.pdf
Fisher St - Morley Av / Oakwood Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 7, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Fisher Street_Oakwood Ave to Arnold Ave.pdf
Goulet St - Traverse Av / Youville St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start May 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Bituminex Paving Ltd
Additional information Click here
Document
2023 Construction Notice_Goulet St.pdf
Jubilee Av - Cockburn St S / Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 8, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Document
2023 Construction Notice_Jubilee Ave.pdf
Langside St - Cumberland Av / Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start May 15, 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Wintec
Document
2023 Construction Notice_Langside St.pdf
Larkin Cv - Brentlawn Bv / End   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Linacre Rd - Radcliffe Rd / Michigan Av   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Manahan Av - Pembina Hw / Hudson St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start July 31, 2023
Estimated to end Summer 2024
Approx. % completed 90
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_Manahan Ave.pdf
Moberly Av - Sanford Fleming Rd / Cambie Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start September 21, 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant WSP Canada Inc
Contractor Bituminex Paving Ltd
Document
2023 Construction Notice_Moberly Avenue.pdf
Redwood Av - Salter St / Main St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start August 2022
Estimated to end Summer 2024
Approx. % completed 70
Consultant KGS Group Limited
Contractor Darco Enterprises
Document
2022 Preconstruction Notice_Redwood Ave.pdf
Refinery District BRT Pathway Connection   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 50
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Refinery District BRT.pdf
Renfrew St - John Brebeuf Pl / Grant Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group
Contractor Bituminex Paving Ltd
Document
2023 Preconstruction Notice_Renfrew St.pdf
River Av - Osborne St / Wellington Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start June 2023
Estimated to end Summer 2024
Approx. % completed 60
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Preconstruction Notice_Wellington.pdf
St Vital Bridge   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Wellington Cr - River Av / Stradbrook Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start August 14, 2023
Estimated to end Summer 2024
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor Darco Enterprises
Document
2023 Construction Notice_River Avenue West and Wellington Crescent.pdf
Wildwood G Pk - South Dr / Wildwood St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 17, 2023
Estimated to end Summer 2024
Approx. % completed 60
Consultant AECOM Canada Ltd
Contractor JC Paving
Wildwood H Pk - South Dr / South Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start October 10, 2023
Estimated to end Summer 2024
Approx. % completed 60
Consultant AECOM Canada Ltd
Contractor JC Paving
Document
2023 Construction Notice_Wildwood Park H - South Drive to South Drive.pdf
Woodchester By - Cathcart St/Cathcart St   View Map
Facility type Street
Type of work TBO
Estimated to start Summer 2023
Estimated to end Summer 2024
Approx. % completed 80
Consultant KGS Group Limited
Contractor J Con Civil

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.


Was this information helpful?

How can we make this web page better?

Information collected will be used to improve our website. Do not use this form to submit a request for service or information because it will not be forwarded to departments for response. To submit a request for service or information, contact 311.

This form is not intended to collect personal information; however, any personal information you choose to include in your comments is collected by the City of Winnipeg under the authority of section 36(1)(b) of the Freedom of Information and Protection of Privacy Act for the purpose of improving our website and will not be used or disclosed for any other purposes, except as authorized by law. Contact the Corporate Access and Privacy Officer by mail (City Clerk’s Department, Susan A. Thompson Building, 510 Main Street, Winnipeg MB, R3B 1B9) or by telephone (311) if you have any questions about the collection of this information.

Ces renseignements sont-ils utiles?

Comment pourrait-on améliorer cette page Web?

Les renseignements recueillis serviront à l’amélioration de notre site Web. Prière de ne pas se servir de ce formulaire pour soumettre une demande de service ou de renseignements, car la demande ne sera pas transmise au service en question. Pour soumettre une demande de service ou de renseignements, veuillez communiquer avec le 311.

Le présent formulaire ne vise pas à recueillir des renseignements personnels. Cependant, les renseignements personnels que vous choisissez d’inclure dans vos commentaires sont recueillis par la Ville de Winnipeg en conformité avec l’alinéa 36(1)b) de la Loi sur l’accès à l’information et la protection de la vie privée dans le but d’améliorer son site Web et ne seront ni utilisés ni divulgués pour d’autres raisons, sauf dans les cas où cela est autorisé par la loi. Communiquez avec l’agent de l’accès à l’information et de la protection de la vie privée de la Ville par courrier au Bureau du greffier, immeuble Susan-A.-Thompson, 510, rue Main, Winnipeg (Manitoba) R3B 1B9, ou par téléphone au 311 si vous avez des questions sur la collecte de ces renseignements.