Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on January 18, 2026 @ 2:30 PM)
+
Abinojii Mikanah (WB) - Dakota St / St Marys Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Abinojii Mikanah WB to Pembina Hw NB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Academy Rd / Kingsway - Oak St / Ash St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Addington By - Oakdale Dr / End
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Addington By - Oakdale Dr / End
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Adsum Dr / Sasaki Cr - Sorokin St / Sasaki Cr
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Alenbrook By - Alenbrook By / End
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Arlington St - Enniskillen Av / Lansdowne Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Arlington St - Lansdowne Av / Inkster Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Assiniboine Park Pedestrian Bridge
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2025
Approx. % completed
0
+
Austin St - Higgins Av / Henry Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bannatyne Av / McDermot Av - Tecumseh St / Arlington St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Barry Av - Plessis Rd / Robson St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bayne Cr / London St - Bayne Cr / Tu Pelo Av
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bayview Pl - Paulley Dr / McMeans Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
Beaverhill Bv - Beaverhill Bv / Beaverhill Bv
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beaverhill Bv - Fermor Av / Park Terrace Dr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beaverhill Bv - Park Terrace Dr / Fermor Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beaverhill Bv - Park Terrace Dr / Shamrock Dr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Beecher Av / Templeton Av - Brambleberry Pl / Garden Park Dr
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Beeston Dr - Seaforth Av / Seaforth Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Beliveau Rd - Kearney St / Dakota St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bellavista Cr - Voyageur Av / Rogan Dr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Berrydale Av - End / St Annes Rd
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Blanchard Av - Middle Gate / West Gate
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Tetra Tech
Document
+
Boston Av - Morley Av / Hudson St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Bradford St - Saskatchewan Av / Wellington Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Brock St - Grant Av / Mathers Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St
View Map
Facility type
Alley
Type of work
Renewal
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St
View Map
Facility type
Alley
Type of work
Renewal
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Brophy Av / Ostafiew Farm Rd - Foyle St / Dexter St
View Map
Facility type
Alley
Type of work
Renewal
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Bury St - Whyte Av / Irysh Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
July 14, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Bushnell St - Logan Av / Alexander Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Carlaw Av - Nassau St S / Daly St S
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Carlton St - Cumberland Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Carlton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Carlton St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Carlton St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Carlton St - York Av / Broadway
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Carrigan Pl - Ulster St / Lane
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Carruthers Av - Cottingham St / 1037 Lansdowne Ave
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Carter Av - Pembina Hw / Lilac St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Chancellor Dr - Markham Rd / Path
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Charles St - Jarvis Av / Sutherland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Contractor
Darco Enterprises
+
Chatham Pl - Morningside Dr / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 11, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Chopin Bv - Wiebes Dr / Uxbridge Rd N
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Cora Av - Whitegates Cr / Maureen St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Crescent Dr - 758 Crescent Dr / Pembina Hw
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Crowson By - Dowker Av / Dowker Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Day St - Kildare Av E / Victoria Av E
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Day St - Regent Av E / Victoria Av E
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Day St - Victoria Av E / Regent Av E
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Dells Cr - Wales Av / Hazelwood Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Overlay
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Devonshire Dr / Whiteway Rd - Clouston Dr / Sanford Fleming Rd
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Dubois Pl/Champagne Cr - Champagne Cr/Lamirande Pl
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Dufferin Av - Powers St / McGregor St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Dzyndra Cr - Hatcher Rd / Bournais Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
East Gate - Blanchard Av / Middle Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Tetra Tech
Document
+
Edmonton St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Edmonton St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Edmonton St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Edmonton St - St Mary Av / Broadway
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Elgin Av - Isabel St / Sherbrook St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Elgin Av W - Worth St / Keewatin St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
English Pl - Darwin St / Darwin St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Ghent Cv - Mayfield Cr / Mayfield Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 2, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Golf Bv - McBey Av / Meadowside Dr
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Goulding St - Ellice Av / St Matthews Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Goulding St - Sargent Av / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Goulding St - Wolever Av / Portage Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grant Av - Harrow St / Grant Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grant Av - Wilton St / Grant Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Greenacre Bv - Portage Av / McBey Av
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Greenlea Cv - Gilmore Av / Gilmore Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Grosvenor Av / Corydon Av - Cordova St / Campbell St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Gunnell St - Henry Av / Logan Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Hargrave St - Cumberland Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Hargrave St - Ellice Av / Cumberland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Hargrave St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Harriet St - Bannatyne Av / McDermot Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Harriet St - McDermot Av / Notre Dame Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Hector Av E - Lilac St / Wentworth St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Fall 2025
Estimated to end
Summer 2026
Approx. % completed
10
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Hector Av W - Wentworth St / Stafford St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Fall 2025
Estimated to end
Summer 2026
Approx. % completed
10
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Helmsdale Av / Kimberly Av - Raleigh St / Golspie St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Henry Av - Gunnell St / Sherbrook St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Huntleigh St - St Matthews Av / Portage Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
KGS Group
+
Irysh Av - Bury St / Blake St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 14, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Jarvis Av - Andrews St / McGregor St
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Jarvis Av - McGregor St / McKenzie St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Jarvis Av - McKenzie St / Parr St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Jarvis Av - Powers St / Andrews St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Johnson Av E - Grey St / Gateway Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kate St - Elgin Av / William Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
July 21,2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Kennedy St - St Mary Av / York Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Kennedy St - York Av / Broadway
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Kennedy St - Ellice Av / Qu'Appelle Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Kennedy St - Graham Av / St Mary Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Kennedy St - Portage Av / Graham Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Kennedy St - Qu'Appelle Av / Cumberland Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kent Rd - Beach Av / Talbot Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kent Rd - Keenleyside St / Chalmers Av E
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kent Rd - Talbot Av / Nairn Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kilmer Av - Carroll Rd / Longfellow By
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kings Dr - Silverstone Av / Kilkenny Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kings Dr - U of M Campus / Silverstone Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Kingsway / Grosvenor Av - Lindsay St / Railway Tracks
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
La Porte Pl/Le Maire St - La Porte Pl/Le Maire St
View Map
Facility type
Alley
Type of work
Asphalt Overlay
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Almey Av / CNR Overpass
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - CNR Overpass / Grassie Bv
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Concordia Av E / Lagimodiere Bv
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Grassie Bv / CNR Overpass
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv - Lagimodiere Bv / Concordia Av E
View Map
Facility type
Street
Type of work
Preservation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lagimodiere Bv Overpass over CPR Keewatin
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Leila Ave - McPhillips St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
+
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lindenwood Dr E - Lindenwood Dr E / Lindenwood Dr E
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lindenwood Dr W - Lindenwood Dr W / Lindenwood Dr W
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lindenwood Dr W - Lindenwood Dr W / Lindenwood Dr W
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Litz Pl - Henderson Hw / Appleton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lodge / Portage Av - Wallasey St / Thompson Dr
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lodge Av / Portage Av - Aldine St / Wallasey St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lodge Av / Portage Av - Vernon Rd / Whytewold Rd
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Lodge Av / Portage Av - Whytewold Rd / Olive St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Logan Av - Omands Creek Bv / Brookside Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
London St / McCreedy Rd - Amelia Cr / Tu Pelo Av
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Manhattan Av - Stapleton St / Keenleyside St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Marcus Pl - Whiteway Rd / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 18, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Marigold By - Sinclair St / Sinclair St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Marshall Cr - Waller Av / Clarence Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 30, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Martha St - Henry Av / Logan Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McDermot Av / Notre Dame Av - Notre Dame Av / Tecumseh St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
McDermot Av / Notre Dame Av - Princess St / Adelaide St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McFarlane St N - Rover Av / Sutherland Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 15, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
KGS Group
Contractor
JC Paving
Document
+
McGregor St - Selkirk Av / Dufferin Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
McKenzie St - Hartford Av / Jefferson Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
McKenzie St - Kingsbury Av / Hartford Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
McMicken St - Sargent Av / Ellice Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
+
McMillan Av / Corydon Av - Hugo St N / Cockburn St N
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
McMullen Cr - Hatcher Rd / Hatcher Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
McPhillips St - Emes Rd / North Point Bv
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Middle Gate - Cornish Av / East Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
Tetra Tech
Document
Facility type
Bridge
Type of work
Maintenance
Estimated to start
August 2025
Estimated to end
Summer 2026
Approx. % completed
80
Document
+
Nassau St S - Brandon Av / Hethrington Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Nassau St S - Hethrington Av / Morley Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Nolin Av/Nolin Av - Dubois Pl/Nolin Av
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Nolin Av/Nolin Av - Dubois Pl/Nolin Av
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2026
Estimated to end
Fall 2027
Approx. % completed
Planned
+
Northwest Hydro Corridor Pathway - Church Av to McPhillips Street Casino
View Map
Facility type
Pedestrian / Cycling
Type of work
New - Pedestrian / Cycling
Estimated to start
Summer 2026
Estimated to end
Fall 2027
Approx. % completed
Planned
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
0
Consultant
Barnes and Duncan
Document
+
Osborne St - Baltimore Rd / Rosedale Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
Stantec Consulting Ltd
+
Osborne St - Rosedale Av / St Vital Bridge
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
Stantec Consulting Ltd
+
Osborne St/Nassau St S - Kylemore Av/Walker Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Osborne St/Nassau St S - Walker Av/Rathgar Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
+
Panet Rd - Nairn Av / CPR TRacks
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Parker Av - Derek St / Daniel St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Parker Av - Wynne St / Derek St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Parkville Dr - Dunkirk Dr / Pulberry St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Paufeld Dr - Karen St / Rothesay St
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Paulley Dr - Redonda St / Dowling Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 21, 2025
Estimated to end
Summer 2026
Approx. % completed
80
Consultant
WSP Canada Inc
Document
+
Peacock Pl - End / Lake Grove By
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Pembina Highway Bridge over Abinojii Mikanah Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Pembina Hw NB to Abinojii Mikanah EB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
Planned
+
Pembina Hw NB to Abinojii Mikanah WB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
Planned
Document
+
Pembina Hw SB to Abinojii Mikanah EB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Pembina Hw SB to Abinojii Mikanah WB
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
10
Document
+
Perth Av - McGregor St / Parr St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Plessis Rd - 560 Plessis Rd / St Boniface Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Plessis Rd - 996 Plessis Rd / St Boniface Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Plessis Rd - St Boniface Rd / 560 Plessis Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Plumtree Pl - Meadowood Dr / Meadowood Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Poplynn Dr - Egesz St / Egesz St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Portage Av - Banting Dr / Sturgeon Rd
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Portage Av - David St / Cavalier Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Portage Av - Sturgeon Rd / Cavalier Dr
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
July 28, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
Stantec Consulting Ltd
Contractor
Bayview Construction Ltd
Document
+
Portage Av / Allard Av - Best St / Bedson St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av / Allard Av - Best St / Bedson St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Portage Av / Picardy Pl - Broadway / Canora St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Prince Edward St - Rover Av / Lane
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
KGS Group
Contractor
JC Paving
Document
+
Qu'Appelle Av - Balmoral St / Kennedy St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Document
+
Radar Pl - Voyageur Av / Rogan Dr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Raquette St - Browning Bv / Assiniboine Av
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Regent Av E / Melrose Av E - Kanata St / Day St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rogan Dr - Bellavista Cr / Hamilton Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Roslyn Rd / River Av - Roslyn Rd / Nassau St N
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rosseau Av W / Ravelston Av W - Brewster St / Plessis Rd
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rover Av - Angus St / Annabella St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rover Av - Barber St / Hallet St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rover Av - Disraeli St / Barber St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Rupert Av - Martha St / Main St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
+
Sage North Development Phase 1A Contract 5A
View Map
Facility type
Street
Type of work
New - Street Construction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sage North Development Phase 1A Contract 5C
View Map
Facility type
Street
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sandralin By - End / Avalon Rd
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sargent Av - Balmoral St / Edmonton St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av - Furby St / Balmoral St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
AECOM Canada Ltd
+
Sargent Av / Ellice Av - Downing St / Minto St
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sawchuk By - Antrim Rd / Antrim Rd
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Scotia St - Armstrong Av/Newton Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Seaforth Av - Main St / Aikins St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Sherbrook St - Henry Av / Logan Av
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sims Cr - Hatcher Rd / Hatcher Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 10, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
St Anthony Av - Andrews St / McGregor St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
St Anthony Av - McGregor St / Parr St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
St Mary Av - Edmonton St / Memorial Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
St Marys Rd - Dakota St / Fermor Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Rd - Fermor Av / West Fernwood Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Rd - Molgat Av / Moore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Rd - Moore Av / Arden Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Rd - PTH 100 / Chrypko Dr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Marys Rd - West Fernwood Av / Molgat Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Matthews Av / Silver Av - Madison St / Kensington St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
St Matthews Av / Wolever Av - Strathcona St / Railway Tracks
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sunglow Rd - Dawnville Dr / Kildonan Meadow Dr
View Map
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Sweetwood By - Forest Park Dr / Forest Park Dr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
University Cr - 80m North of Dysart Rd/Thatcher Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
University Cr - Markham Rd / 80m North of Dysart Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
Document
+
Waller Av - Pembina Hw / Lane West of Donnelly St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Spring 2026
Estimated to end
Fall 2026
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Asphaltec Paving
Document
Facility type
Street
Type of work
TBO
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
City Of Winnipeg - Engineering Division
+
Waterbury Dr - Lindenwood Dr E / Lindenwood Dr E
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Weatherdon Av - Stafford St / Harrow St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
West Av - Rouge Rd / Whitegates Cr
View Map
Facility type
Street
Type of work
Major Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
West Gate - Blanchard Av / Middle Gate
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
Tetra Tech
Document
+
Whiteway Rd - Clouston Dr / Sanford Fleming Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 18, 2025
Estimated to end
Summer 2026
Approx. % completed
70
Consultant
WSP Canada Inc
Document
+
Whyte Av - East of Vine St / Quelch St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 8, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Whyte Av - Quelch St / Bury St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 8, 2025
Estimated to end
Summer 2026
Approx. % completed
90
Consultant
KGS Group
Contractor
JC Paving
Document
+
Wilkes Av - 400m W of Charleswood Rd / PTH 100
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Wilkes Av - Harstone Rd / 400m E of Charleswood Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Woodfield By / Woodfield By - Woodfield By / Cathcart St
View Map
Facility type
Alley
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Yale Av W - Bond St / Winona St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
York Av - Carlton St / Kennedy St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
York Av - Kennedy St / Vaughan St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
York Av - Vaughan St / Memorial Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
+
Zeglinski Cr - Wiebes Dr / Zeglinski Cr
View Map
Facility type
Street
Type of work
Minor Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.