Road construction list
The roadway construction list provides project information in alphabetical order by street name.
Project information is available by location in both map and list format.
More information: Lane closures
How to use the construction list
Click on the + beside the project name. A dropdown box will appear with these project details:
type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
estimated to start,
estimated to end,
approximate percentage completed:
Pre-Construction – Construction phase has not started.
0% – Construction contract is in place, but crews have not mobilized to the site.
5% – Crews have mobilized to the site and construction has just begun.
10% 90% – An approximation of progress; construction is well underway.
95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
consultant information, and
contractor information.
You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.
Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.
City of Winnipeg - Public Works Capital Projects
(Last updated on December 26, 2024 @ 12:30 PM)
+
Assiniboine Park Pedestrian Bridge
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Cadiz By - Malone St / Buckle St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Cumberland Av/Carlton St - Cumberland Av/Qu'Appelle Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
+
Cumberland Av/Hargrave St - Cumberland Av/Ellice Av
View Map
Facility type
Alley
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
AECOM Canada Ltd
Document
+
Dearborn Av - Lacy St / Brazier St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
70
Consultant
Dillon Consulting Limited
+
Eldridge Av - Elmhurst Rd / Haney St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Ellice Av - Strathcona St / Empress St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 26, 2024
Estimated to end
Summer 2025
Approx. % completed
90
Consultant
WSP Canada Inc
Document
+
Fortier Av - Summerfield Wy / Pentland St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Freemont By - Fairlane Av / Fairlane Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Gerrond By - Cavalier Dr / Cavalier Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
June 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
KGS Group
Document
+
Ghent Cv - Mayfield Cr / Mayfield Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Gordon Av - Stadacona St / Brazier St
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
Dillon Consulting Limited
+
Green Valley By - Louelda St / Louelda St
View Map
Facility type
Street
Type of work
TBO
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Hood Av - Scarfe St / Leahcrest Cr
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
October 14, 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
Document
+
Irene St - Sony Pl / Waller Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
May 27, 2024
Estimated to end
Summer 2025
Approx. % completed
20
Consultant
WSP Canada Inc
Contractor
Darco Enterprises
Document
+
Kullman St - Snowdon Av / Kimberly Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
+
McGregor St - Alley South of Partridge Av / Kingsbury Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
WSP Canada Inc
Contractor
Bayview Construction Ltd
Document
+
Melrose Av E - Leola St / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
Dillon Consulting Limited
+
Montgomery Av - Fisher St / Casey St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
KGS Group
Document
+
Nassau St S - Jubilee Av / McNaughton Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
KGS Group
Document
+
Nassau St S - McNaughton Av / Montague Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
August 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
KGS Group
Document
+
Norilyn By - Antrim Rd / Antrim Rd
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Norwood & Main Street Bridge NB & SB Rehabilitation
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
+
Osborne St - Baltimore Rd / Rosedale Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Osborne St - Rosedale Av / St Vital Bridge
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Consultant
Morrison Hershfield Limited
+
Pembina Highway Bridge over LaSalle River Rehabilitation (SB)
View Map
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
Planned
Document
+
Portage Ave and Main Street Pedestrian Opening
View Map
Facility type
Sidewalk
Type of work
New Facility
Estimated to start
Winter 2024 - 2025
Estimated to end
Summer 2025
Approx. % completed
0
Consultant
Dillon
Additional information
Click here
Document
+
Roanoke St - Melrose Av E / Pandora Av E
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
5
Consultant
Dillon Consulting Limited
+
Rudolph By - Snowdon Av / Snowdon Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
+
Snowdon Av - Treger By / Molson St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
Summer 2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Facility type
Bridge
Type of work
Rehabilitation
Estimated to start
Summer 2023
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
Morrison Hershfield Limited
+
Summerfield Wy - Gilmore Av / Gilmore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Taylor Av (EB) - Renfrew St / Lindsay St
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Taylor Av (WB) - Lindsay St / Kenaston Bv
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
May 27, 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
Dillon Consulting Limited
Contractor
JC Paving
Document
+
Tranquility Cv - Summerfield Wy / Gilmore Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
September 9,2024
Estimated to end
Summer 2025
Approx. % completed
60
Consultant
Dillon Consulting Limited
Document
+
Turnbull Dr - Pembina Hw / City Limit
View Map
Facility type
Street
Type of work
Mill and Fill
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
Morrison Hershfield Limited
Contractor
Bayview Construction Ltd
Document
+
University Cr - 80m North of Dysart Rd/Thatcher Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
University Cr - Markham Rd / 80m North of Dysart Rd
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
Fall 2024
Estimated to end
Summer 2025
Approx. % completed
40
Consultant
AECOM Canada Ltd
Contractor
Bayview Construction Ltd
Additional information
Click here
+
Wabasha St - Regent Av E / Pandora Av E
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
September 23, 2024
Estimated to end
Summer 2025
Approx. % completed
80
Consultant
Dillon Consulting Limited
Document
+
Westgrove Wy - Dale Bv / Dale Bv
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Wicklow St - North Dr / Waterford Av
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Wicklow St - Oakenwald Av / Dowker Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Wicklow St - Point Rd / North Dr
View Map
Facility type
Street
Type of work
Reconstruction
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
Wicklow St - Waterford Av / Oakenwald Av
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
+
William Clement Parkway Pathway - Grant Ave/Oakdale Dr
View Map
Facility type
Pedestrian / Cycling
Type of work
Reconstruction
Estimated to start
August 19, 2024
Estimated to end
Summer 2025
Approx. % completed
50
Consultant
City Of Winnipeg - Engineering Division
Document
+
Woodgrove St - Southwood Av / End
View Map
Facility type
Street
Type of work
Rehabilitation
Estimated to start
To Be Determined
Estimated to end
To Be Determined
Approx. % completed
0
Consultant
KGS Group
Document
Disclaimer and Indemnity:
The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.
The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.
By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.